Hand over of Testware is a part of which Phase:

  1. Test Analysis and Design
  2. Test Planning and control
  3. Test Closure Activities
  4. Evaluating exit criteria and reporting

Answer(s): C



View Related Case Study

One Key reason why developers have difficulty testing their own work is:

  1. Lack of technical documentation
  2. Lack of test tools on the market for developers
  3. Lack of training
  4. Lack of Objectivity

Answer(s): C



View Related Case Study

The purpose of exit criteria is:

  1. Define when to stop testing
  2. End of test level
  3. When a set of tests has achieved a specific pre condition
  4. All of the above

Answer(s): D



View Related Case Study

What is important to do when working with software development models?

  1. To adapt the models to the context of project and product characteristics.
  2. To choose the waterfall model because it is the first and best proven model.
  3. To start with the V-model and then move to either iterative or incremental models.
  4. To only change the organization to fit the model and not vice versa.

Answer(s): A