Microsoft MB-335 Exam Questions
Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert (Page 3 )

Updated On: 5-Mar-2026
View Related Case Study

HOTSPOT

You need to configure each item for plastic manufacturing.

Which production types should you use? To answer, select the appropriate options in the answer area.

Note: Each correct selection is worth one point.

Hot Area:

  1. See Explanation section for answer.

Answer(s): A



View Related Case Study

HOTSPOT

You need to determine the batch values on the combined mix batches for OperatorA.

Which values should you use? To answer, select the appropriate options in the answer area.

Note: Each correct selection is worth one point.

Hot Area:

  1. See Explanation section for answer.

Answer(s): A

Explanation:

Box 1: Based on batch group
OperatorA must consolidate partial mix batch group runs into saleable package quantities.

To generate a batch number when you create a merged batch, you must assign a batch number group to the released product. Otherwise, you can enter a batch number manually.

Box 2: Manually entered
What if the batches have different batch dates?
If the batches have different batch dates, some of the dates are calculated based on the values in the Batch dates group on the Merged batch FastTab of the Batch merge page. The system calculates values for the fields in the Batch dates group. These values include the manufacturing date, expiration date, shelf advice date, and best-before date. The dates are calculated based on settings for the item in the Item data field group of the Released product details page. You can change the values or enter them manually. For all other dates, no calculation is done. The same principle is used for batch attribute values. If a date is the same for all the source batches, that date is suggested for the merged batch. If the date isn't the same for all source batches, the date is blank on the merged batch, and you can enter it manually.

Box 3: All are retained


Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/inventory/merge-inventory-batches



View Related Case Study

You need to resolve the issue for UserC.

Which two options should you configure? Each correct answer presents a complete solution.

Note: Each correct selection is worth one point.

  1. Shelf life period in days
  2. Backward tracing
  3. Best advice period in days
  4. Best before period in days
  5. Forward tracing

Answer(s): A,D

Explanation:

Scenario:
* UserC learns that mixes containing BaseA have been stamped with a batch date from the flour vendor and is not being calculated from the mix manufacturing date. The mixes from the past month that might be impacted need to be identified and the calculation needs to be corrected.
* BaseA and BaseB are made in large batches and stored until they are used in the other mixes.
* Mixes with BaseA have a shelf life of six months due to the type of flour it uses.
You can reset shelf life dates for an inventory batch.
Use this procedure to reset the shelf life date for an inventory batch. The shelf life defines the effective period of a product as measured in days, months, or years. Reports and picking strategies for products are determined based on the shelf life of a particular lot by using FIFO (First In, First Out) rules.
1.Click Inventory management > Inquiries > Dimensions > Batches.
2.Select the inventory batch to update.
3.Click Reset shelf life dates.
4.In the Reset shelf life dates form, select a new date in the date field that you want to change.
Manufacturing date
Shelf advice date    Select the recommended date when a batch or lot should be retested to validate that it still meets testing standards.
Best before date    Select the date before an inventory batch is best used. If you change the best before date, you are asked whether to recalculate the expiration date.
Note: In the Shelf life period in days field, enter the number of days that are added to the batch date of the item to determine the expiration date of the item.


Reference:

https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/reset-shelf-life-dates-for-an-inventory-batch https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/set-up-an-item-as-a-shelf-life-item



View Related Case Study

HOTSPOT

You need to resolve the issue for UserF.

What should you configure? To answer, select the appropriate options in the answer area.

Note: Each correct selection is worth one point.

Hot Area:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



Box 1: Setup time, Route Group, Resource
Cleaning and setup of machinery between products has been causing delays in production.

Requirements
Production
Similar recipes must be able to be produced in succession to limit machinery cleaning and setup times.

A route defines the process for producing a product or product variant. It describes each step (operation) in the production process and the order that these steps must be performed in. For each step, the route also defines the required operations resources, the required setup time and run time, and how the cost should be calculated.

Box 2: Operations scheduling with Finite material only
All costs must be tracked for each production run and be able to be reconciled at the end of the monthly accounting cycle, including any work in process (WIP) costs and donations.

Operations scheduling, Finite materials
If you're working with finite materials, scheduling also depends on the availability of the materials that are required for production. If there aren't enough available components for the production, production can be delayed. You can base scheduling on the use of materials by specifying the materials that must be available for production.
When you optimize on both resource capacity and the availability of materials, production is calculated according to these restrictions. A production order can't be scheduled to start until capacity and materials are available at the same time and in the required quantities.


Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/routes-operations https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/operations-scheduling#finite- materials



View Related Case Study

HOTSPOT

You need to resolve the issue for UserG.

What should you do? To answer, select the appropriate options in the answer area.

Note: Each correct selection is worth one point.

Hot Area:

  1. See Explanation section for answer.

Answer(s): A

Explanation:

Box 1: Assign size and color.
UserG must plan the specialty desserts for the current holiday season. Specialty desserts are offered during the holiday season. This year, customers may specify additional icing colors and cake layers when placing orders. Depending on the popularity of two of the new colors, they may be offered the next year.

Box 2: Assign to the Product Variant. Set as inactive after the holiday season, A released product or product variant can be associated with a product lifecycle state that documents in which lifecycle state a specific product or variant is currently in. You can define any number of product lifecycle states by assigning a state name and description. You can select one lifecycle state as the default state for new released products. Released product variants inherit their product lifecycle state from their released product master on creation.
When changing the lifecycle state on a released product master, you can choose to update all existing variants that have the same original state.


Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/pim/product-lifecycle



Viewing page 3 of 55
Viewing questions 11 - 15 out of 270 questions



Post your Comments and Discuss Microsoft MB-335 exam dumps with other Community members:

MB-335 Exam Discussions & Posts

AI Tutor