Free MB-335 Exam Braindumps
Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert Questions 91–95 (page: 20)

Updated On: 10-Feb-2026

You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods.

The company must track variances in material compared to the original estimated amount. You must only use one picking list journal for each production order.

You need to post a picking list that accounts for the material required to produce 105 finished goods.

What should you do?

  1. When creating the lines for a picking list, select the estimated consumption option and override the consumption field with the actual amount to be consumed.
  2. Increase the production order to a total quantity of 105 and re-estimate.
  3. Report as finished five additional units into the good quantity and post a picking list for only the originally estimated amount.
  4. In the Bill of materials production details, edit the estimated amount for each line to equal 105 units of raw material.

Answer(s): A

Explanation:

Correct:
* When creating the lines for a picking list, select the estimated consumption option and override the consumption field with the actual amount to be consumed.
Incorrect:
* In the Bill of materials production details, edit the estimated amount for each line to equal 105 units of raw material.
* Increase the production order to a total quantity of 105 and re-estimate.
* Post a picking list for 100 to account for the originally estimated amount.
* Post a picking list for 100 to account for the originally estimated amount. Post an additional picking list to account for the equivalent amount of material to produce 5 finished goods.Bh5/g6
* Report as finished five additional units into the good quantity and post a picking list for only the originally estimated amount.
Note:
Does the system calculate variances on a production order when I manually enter the cost? Yes, the system calculates variances when you manually enter a standard cost. However, when you manually enter a standard cost instead of calculating it, all material, route, and indirect cost consumptions in the production order are considered a substitution variance. If there are additional variances, such as consumption of extra materials or labor, they will also be recorded as variances from the production BOM. Therefore, we strongly recommend that you always run a calculation for items that have a BOM, route, or indirect costs.


Reference:

https://learn.microsoft.com/en-us/dynamics365/supply-chain/cost-management/inventory-costing-faq



DRAG DROP

A company uses separate finished good item numbers for size variations of the same product.

The company wants to minimize the number of variously-sized items that are created.

You need to perform the setup to allow variants in size to the product master.

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:


Reference:

https://gfeaxblog.wordpress.com/2017/09/28/o365-how-to-create-product-masters/



DRAG DROP

A company makes lubricants and greases used in the automotive industry. The company plans to implement Dynamics 365 Supply Chain Management.

The system must meet the following requirements:

Schedule the batch production of products.

Plan for inventory fluctuations of ingredients that are used across different products.

Schedule delivery of amounts of proprietary compounds used during production from vendors to keep production runs on schedule and eliminating excess stock on hand or delayed production.

You need to perform the initial setup of the company's Dynamics 365 environment.

At which level should you set up the items? To answer, drag the appropriate setup levels to the correct setup options. Each setup level may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

Note: Each correct selection is worth one point.

Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



DRAG DROP

A glass bottle manufacturer uses route operations to schedule resources and track manufacturing costs.

The company has recently seen an increase in demand and purchases another resource that costs more to run. The company uses the same costs per resource. The company must be able to track cost contributions for the new resource.

You need to create a cost category for the new resource.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Note: More than one order of answer choices is correct. You will receive credit for any of the correct orders you select.

Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:


Reference:

https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/cost-management/cost- categories-used-production-routings



A company produces energy-efficient LED lighting solutions. Production is dependent on primary and secondary resources.

The primary resource is skilled assembly workers responsible for assembling LED lighting fixtures. The workers can work on only one fixture at a time during production.

The secondary resource is automated LED soldering machines, which typically operate at a 50% load capacity. The machines can work on multiple LED lighting fixtures at the same time.

The company must optimize the allocation of resources to meet customer demands efficiently.

You need to configure the resources to meet the customer demand.

What should you do?

  1. Navigate to the primary resource and define priority.
  2. Navigate to the primary resource and disable Finite material.
  3. Navigate to the primary resource and enable Exclusive.
  4. Navigate to the primary resource and disable Finite capacity.

Answer(s): C

Explanation:

In Dynamics 365 Supply Chain Management, configuring a primary resource as Exclusive ensures that the workers (primary resource) are allocated to only one production job at a time, as stated in the requirement.
This fits the scenario where the skilled assembly workers can only work on one LED fixture at a time.
Finite capacity allows the system to schedule operations based on available capacity, which is relevant but not specific to the problem of ensuring one worker per fixture.
Priority is used for deciding between competing jobs but does not enforce the one-job-per-worker rule.
Finite material is related to material planning, not resource assignment.



Viewing page 20 of 55
Viewing questions 96 - 100 out of 270 questions


Post your Comments and Discuss Microsoft MB-335 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!