During which stage of risk planning are risks prioritized based on probability and impact?

  1. Identify risks.
  2. Plan risk responses.
  3. Qualitative risk analysis.
  4. Quantitative risk analysis.

Answer(s): C



Company A is working on a project. The project`s budget is 10,000. The planned value as of date X is 4,000. The project is 30% completed. 60% of the budget has been spent to date X. The actual cost (AC) to date for the project is:

  1. 66,000.
  2. 62,400.
  3. 63,000.
  4. 65,000.

Answer(s): A



Which of the following documents are NOT part of the PTA handover from Sales to Delivery?

  1. Cost baseline.
  2. Project management/delivery plan.
  3. Logistics plan.
  4. WBS structure.

Answer(s): D



Which of the following is not chargeable work?

  1. Project management.
  2. Construction works.
  3. Site logistics.
  4. Account management.

Answer(s): D



What does it mean if schedule performance index (SPI) is greaterthan 1?

  1. Good progress as the project is ahead of schedule.
  2. Cost overrun as the rollout is ahead of schedule.
  3. Cost saving as the project will finish earlier.
  4. Deviations in the rollout are negatively impacting the accuracy of the cost forecast.

Answer(s): A