Which of the following are components of the latest estimate in PRS (Profitability Reporting System)?

  1. Sales, cost of sales and gross profit.
  2. Sales, volumes and cost of sales.
  3. Actual results of the previous period.
  4. Baseline, ETC and EAC.

Answer(s): A



Which of the following are key components of a Site Process?

  1. Acceptance milestones, share of responsibilities and invoicing triggers.
  2. Change management process and communication plan.
  3. Master schedule, WBS and rollout plan.
  4. Work Packages, WBS and invoicing triggers.

Answer(s): A



At a given point in time, a project has a CPI = 0.7 and SV = 1 ,000. The project is:

  1. over budget and ahead of schedule.
  2. over budget and behind schedule.
  3. below budget and ahead of schedule.
  4. below budget and behind schedule.

Answer(s): A



What of the following cost components is NOT included in the CBL?

  1. Non conformance costs.
  2. Sub-contracting costs.
  3. Risk contingency.
  4. Base costs.

Answer(s): A