Which does NOT describe how services are provided within a Virtual P3O model?

  1. Staff work across an organization without a physical structure to support them
  2. Resources use embedded consistent standards
  3. Resources are in a single P3O office within a central corporate function
  4. Professional staff are embedded within business teams

Answer(s): C



What is the key benefit of using gated reviews on programmes?

  1. Improved ability to amalgamate information
  2. Improved management across geography
  3. Assured quality of decision support information
  4. Automated business processes

Answer(s): C



Which describes the skills and competencies needed by the roles within a P3O?

  1. All require good PPM skills
  2. All require functional competencies such as finance
  3. All require generic personal skills such as coaching or mentoring
  4. Some require good PPM skills while others need more generic business skills

Answer(s): D



Which of the following actions are recommended when implementing a P3O model with Hub Portfolio Offices?
1. Appoint a P3O Sponsor to act as Senior Responsible Owner
2. Allow temporary offices to define their own standards and processes
3. Run the implementation as a programme with appropriate governance
4. Use appropriate programme management lifecycles and processes

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): C



Which is part of the business governance structure whose requirements MUST be met by the reporting of a P3O?

  1. Senior Management Board
  2. External stakeholders
  3. Component offices within the P3O
  4. HeadofP3O

Answer(s): A