Which item is an example of personnel assessment?

  1. Resource calendar
  2. Tight matrix
  3. Team-building activity
  4. Focus group

Answer(s): D



The Plan Stakeholder Management process belongs to which Process Group?

  1. Executing
  2. Initiating
  3. Planning
  4. Monitoring and Controlling

Answer(s): C

Explanation:

Planning Process Group
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management



Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

  1. Feedback analysis
  2. Stakeholder analysis
  3. Communication management plan
  4. Stakeholder management plan

Answer(s): D

Explanation:

13.2.3.1 Stakeholder Management Plan
The stakeholder management plan is a component of the project management plan (Section 4.2.3.1) and identifies the management strategies required to effectively engage stakeholders. The stakeholder management plan can be formal or informal, highly detailed or broadly framed, based on the needs of the project.
In addition to the data gathered in the stakeholder register, the stakeholder management plan often provides: Desired and current engagement levels of key stakeholders;
Scope and impact of change to stakeholders;
identified interrelationships and potential overlap between stakeholders; Stakeholder communication requirements for the current project phase;
Information to be distributed to stakeholders, including language, format, content, and level of detail; Reason for the distribution of that information and the expected impact to stakeholder engagement; Time frame and frequency for the distribution of required information to stakeholders; and
Method for updating and refining the stakeholder management plan as the project progresses and develops. Project managers should be aware of the sensitive nature of the stakeholder management plan and take appropriate precautions. For example, information on stakeholders who are resistant to the project can be

potentially damaging, and due consideration should be given regarding the distribution of such information. When updating the stakeholder management plan, the validity of underlying assumptions should be reviewed to ensure continued accuracy and relevancy.

13.3 Manage Stakeholder Engagement
Definition: The process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle.
Key Benefit: The key benefit of this process is that it allows the project manager to increase support and minimize resistance from stakeholders, significantly increasing the chances to achieve project success.

Inputs
1. Stakeholder management plan
2. Communications management plan
3. Change log
4. Organizational process assets

Tools & Techniques
1. Communication methods
2. Interpersonal skills
3. Management skills

Outputs
1. Issue log
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates



A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

  1. Benchmarking.
  2. Context diagrams.
  3. Brainstorming.
  4. Prototyping.

Answer(s): D

Explanation:

5.2.2.8 Prototypes Prototyping is a method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it. Since a prototype is tangible, it allows stakeholders to experiment with a model of the final product rather than being limited to discussing abstract representations of their requirements. Prototypes support the concept of progressive elaboration in iterative cycles of mock-up creation, user experimentation, feedback generation, and prototype revision. When enough feedback cycles have been performed, the requirements obtained from the prototype are sufficiently complete to move to a design or build phase. Storyboarding is a prototyping technique showing sequence or navigation through a series of images or illustrations. Storyboards are used on a variety of projects in a variety of industries, such as film, advertising, instructional design, and on agile and other software development projects. In software development, storyboards use mock-ups to show navigation paths through webpages, screens, or other user interfaces.



Page 13 of 276



Post your Comments and Discuss PMI CAPM exam with other Community members:

Zee commented on September 21, 2024
Are these useful for CAPM exam in 2024?
SOUTH AFRICA
upvote

DonPook commented on August 18, 2024
Is there any difference in downloading the PDF (paying), to the questions provided for free?
Anonymous
upvote

Sharon commented on August 17, 2024
Which exam questions pack can one use inpreparation for the CAPM exam?
Anonymous
upvote

Priyo commented on November 14, 2023
i used this site since 2000, still great to support my career
INDONESIA
upvote

Priyo commented on November 14, 2023
I used this site since 2000, still great to support my career
INDONESIA
upvote

Shayan commented on June 19, 2023
I am here to let you know that about 4 or 5 new questions are added to this exam. I took the exam today and saw those new questions which are not in your exam dumps. I still passed and got 91%.
UNITED STATES
upvote

Roberto commented on May 04, 2021
This is a good hack to pass the exam.
ITALY
upvote

LarBear commented on January 25, 2019
I have used brain dumps before and working great.
UNITED STATES
upvote

Adrian commented on August 11, 2018
The test engine is for windows only so does not work on my mac (I knew this before purchasing as they mention this on the website). The Android app crashes when I try to activate. I purchased from here because of the apps since I can get the pdf questions from several places on the web. Disappointed customer. Try somewhere else.
UNITED STATES
upvote

Life commented on June 22, 2018
Good CAPM questions AND GUIDE!
UNITED STATES
upvote