Free CAPM Exam Braindumps (page: 19)

Page 19 of 276

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

  1. Bottom-up
  2. Parametric
  3. Analogous
  4. Three-point

Answer(s): C



Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

  1. Direct
  2. Interactive
  3. Pull
  4. Push

Answer(s): D

Explanation:

10.1.2.4 Communication Methods
There are several communication methods that are used to share information among project stakeholders. These methods are broadly classified as follows:
Interactive communication. Between two or more parties performing a multidirectional exchange of information. It is the most efficient way to ensure a common understanding by all participants on specified topics, and includes meetings, phone calls, instant messaging, video conferencing, etc.
Push communication. Sent to specific recipients who need to receive the information. This ensures that the information is distributed but does not ensure that it actually reached or was understood by the intended audience. Push communications include letters, memos, reports, emails, faxes, voice mails, blogs, press releases, etc.
Pull communication. Used for very large volumes of information, or for very large audiences, and requires the recipients to access the communication content at their own discretion. These methods include intranet sites, e-learning, lessons learned databases, knowledge repositories, etc.
The choices of communication methods that are used for a project may need to be discussed and agreed upon by the project stakeholders based on communication requirements; cost and time constraints; and familiarity and availability of the required tools and resources that may be applicable to the communications process.



Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

  1. Cost variance (CV)
  2. Cost performance index (CPI)
  3. Budget at completion (BAC)
  4. Variance at completion (VAC)

Answer(s): B

Explanation:

CPI = EV / AC



Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

  1. Direct and Manage Project Work
  2. Develop Project Management Plan
  3. Plan Quality Management
  4. Monitor and Control Project Work

Answer(s): B

Explanation:

Process: 4.2. Develop Project Management Plan
Definition: The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project’s integrated baselines and subsidiary plans may be included within the project management plan.
Key Benefit: The key benefit of this process is a central document that defines the basis of all project work.

Inputs
1. Project charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Facilitation techniques

Outputs
1. Project management plan

4.2.3.1 Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. Project baselines include, but are not limited to:
Scope baseline (Section 5.4.3.1), Schedule baseline (Section 6.6.3.1), and Cost baseline (Section 7.3.3.1).

Subsidiary plans include, but are not limited to:
Scope management plan (Section 5.1.3.1), Requirements management plan (Section 5.1.3.2), Schedule management plan (Section 6.1.3.1), Cost management plan (Section 7.1.3.1),
Quality management plan (Section 8.1.3.1), Process improvement plan (Section 8.1.3.2),
Human resource management plan (Section 9.1.3.1), Communications management plan (Section 10.1.3.1), Risk management plan (Section 11.1.3.1), Procurement management plan (Section 12.1.3.1), and Stakeholder management plan (Section 13.2.3.1).
Among other things, the project management plan may also include the following:
Life cycle selected for the project and the processes that will be applied to each phase; Details of the tailoring decisions specified by the project management team as follows:
○ Project management processes selected by the project management team,
○ Level of implementation for each selected process,
○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
Description of how work will be executed to accomplish the project objectives;
Change management plan that documents how changes will be monitored and controlled; Configuration management plan that documents how Configuration management will be performed; Description of how the integrity of the project baselines will be maintained;
Requirements and techniques for communication among stakeholders; and
Key management reviews for content, the extent of, and timing to address, open issues and pending decisions.

The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.



Page 19 of 276



Post your Comments and Discuss PMI CAPM exam with other Community members:

Zee commented on September 21, 2024
Are these useful for CAPM exam in 2024?
SOUTH AFRICA
upvote

DonPook commented on August 18, 2024
Is there any difference in downloading the PDF (paying), to the questions provided for free?
Anonymous
upvote

Sharon commented on August 17, 2024
Which exam questions pack can one use inpreparation for the CAPM exam?
Anonymous
upvote

Priyo commented on November 14, 2023
i used this site since 2000, still great to support my career
INDONESIA
upvote

Priyo commented on November 14, 2023
I used this site since 2000, still great to support my career
INDONESIA
upvote

Shayan commented on June 19, 2023
I am here to let you know that about 4 or 5 new questions are added to this exam. I took the exam today and saw those new questions which are not in your exam dumps. I still passed and got 91%.
UNITED STATES
upvote

Roberto commented on May 04, 2021
This is a good hack to pass the exam.
ITALY
upvote

LarBear commented on January 25, 2019
I have used brain dumps before and working great.
UNITED STATES
upvote

Adrian commented on August 11, 2018
The test engine is for windows only so does not work on my mac (I knew this before purchasing as they mention this on the website). The Android app crashes when I try to activate. I purchased from here because of the apps since I can get the pdf questions from several places on the web. Disappointed customer. Try somewhere else.
UNITED STATES
upvote

Life commented on June 22, 2018
Good CAPM questions AND GUIDE!
UNITED STATES
upvote