Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

  1. External
  2. Internal
  3. Mandatory
  4. Discretionary

Answer(s): D

Explanation:

6.3.2.2 Dependency Determination
Dependencies may be characterized by the following attributes: mandatory or discretionary, internal or external, as described below. Dependency has four attributes, but two can be applicable at the same time in following ways: mandatory external dependencies, mandatory internal dependencies, discretionary external dependencies, or discretionary internal dependencies.

Mandatory dependencies. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work. Mandatory dependencies often involve physical limitations, such as on a construction project, where it is impossible to erect the superstructure until after the foundation has been built, or on an electronics project, where a prototype has to be built before it can be tested.

Mandatory dependencies are also sometimes referred to as hard logic or hard dependencies. Technical dependencies may not be mandatory. The project team determines which dependencies are mandatory during the process of sequencing the activities. Mandatory dependencies should not be confused with assigning schedule constraints in the scheduling tool.

Discretionary dependencies. Discretionary dependencies are sometimes referred to as preferred logic, preferential logic, or soft logic. Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal. The project team determines which dependencies are discretionary during the process of sequencing the activities.
External dependencies. External dependencies involve a relationship between project activities and non- project activities. These dependencies are usually outside the project team’s control. For example, the testing activity in a software project may be dependent on the delivery of hardware from an external source, or governmental environmental hearings may need to be held before site preparation can begin on a construction project. The project management team determines which dependencies are external during the process of sequencing the activities.
Internal dependencies. Internal dependencies involve a precedence relationship between project activities and are generally inside the project team’s control. For example, if the team cannot test a machine until they assemble it, this is an internal mandatory dependency. The project management team determines which dependencies are internal during the process of sequencing the activities.



Sensitivity analysis is typically displayed as a/an:

  1. Decision tree diagram.
  2. Tornado diagram.
  3. Pareto diagram.
  4. Ishikawa diagram.

Answer(s): B

Explanation:

11.4.2.2 Quantitative Risk Analysis and Modeling Techniques
• Sensitivity analysis. Sensitivity analysis helps to determine which risks have the most potential impact on the project. It helps to understand how the variations in project’s objectives correlate with variations in different uncertainties. Conversely, it examines the extent to which the uncertainty of each project element affects the objective being studied when all other uncertain elements are held at their baseline values. One typical display of sensitivity analysis is the tornado diagram (Figure 11-15), which is useful for comparing relative importance and impact of variables that have a high degree of uncertainty to those that are more stable. The Tornado diagram is also helpful in analyzing risk-taking scenarios enabled on specific risks whose quantitative analysis highlights possible benefits greater than corresponding identified negative impacts. A tornado diagram is a special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables. In a tornado diagram, the Y-axis contains each type of uncertainty at base values, and the X-axis contains the spread or correlation of the uncertainty to the studied output. In this fgure, each uncertainty contains a horizontal bar and is ordered vertically to show uncertainties with a decreasing spread from the base values.



The Monitoring and Controlling Process Group includes processes that:

  1. Establish the scope, objectives, and course of action of a project.
  2. Define a new project or a new phase of an existing project.
  3. Track, review, and regulate the progress and performance of a project.
  4. Complete the work defined in the project management plan.

Answer(s): C



Which Control Quality tool is also known as an arrow diagram?

  1. Matrix diagram
  2. Affinity diagram
  3. Tree diagram
  4. Activity network diagram

Answer(s): D

Explanation:

8.2.2.1 Quality Management and Control Tools
The Perform Quality Assurance process uses the tools and techniques of the Plan Quality Management and Control Quality processes. In addition, other tools that are available include (see also Figure 8-10):
Affinity diagrams. The affinity diagram is similar to mind-mapping techniques in that they are used to generate ideas that can be linked to form organized patterns of thought about a problem. In project management, the creation of the WBS may be enhanced by using the affinity diagram to give structure to the decomposition of scope.
Process decision program charts (PDPC). Used to understand a goal in relation to the steps for getting to the goal. The PDPC is useful as a method for contingency planning because it aids teams in anticipating intermediate steps that could derail achievement of the goal.
Interrelationship digraphs. An adaptation of relationship diagrams. The interrelationship digraphs provide a process for creative problem solving in moderately complex scenarios that possess intertwined logical relationships for up to 50 relevant items. The interrelationship digraph may be developed from data generated in other tools such as the affinity diagram, the tree diagram, or the fishbone diagram.
Tree diagrams. Also known as systematic diagrams and may be used to represent decomposition hierarchies such as the WBS, RBS (risk breakdown structure), and OBS (organizational breakdown structure). In project management, tree diagrams are useful in visualizing the parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship. Tree diagrams can be depicted horizontally (such as a risk breakdown structure) or vertically (such as a team
hierarchy or OBS). Because tree diagrams permit the creation of nested branches that terminate into a single decision point, they are useful as decision trees for establishing an expected value for a limited number of dependent relationships that have been diagramed systematically.
Prioritization matrices. Identify the key issues and the suitable alternatives to be prioritized as a set of decisions for implementation. Criteria are prioritized and weighted before being applied to all available alternatives to obtain a mathematical score that ranks the options.

Activity network diagrams. Previously known as arrow diagrams. They include both the AOA (Activity on Arrow) and, most commonly used, AON (Activity on Node) formats of a network diagram. Activity network diagrams are used with project scheduling methodologies such as program evaluation and review technique (PERT), critical path method (CPM), and precedence diagramming method (PDM).
Matrix diagrams. A quality management and control tool used to perform data analysis within the organizational structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix.



Page 28 of 276



Post your Comments and Discuss PMI CAPM exam with other Community members:

Zee commented on September 21, 2024
Are these useful for CAPM exam in 2024?
SOUTH AFRICA
upvote

DonPook commented on August 18, 2024
Is there any difference in downloading the PDF (paying), to the questions provided for free?
Anonymous
upvote

Sharon commented on August 17, 2024
Which exam questions pack can one use inpreparation for the CAPM exam?
Anonymous
upvote

Priyo commented on November 14, 2023
i used this site since 2000, still great to support my career
INDONESIA
upvote

Priyo commented on November 14, 2023
I used this site since 2000, still great to support my career
INDONESIA
upvote

Shayan commented on June 19, 2023
I am here to let you know that about 4 or 5 new questions are added to this exam. I took the exam today and saw those new questions which are not in your exam dumps. I still passed and got 91%.
UNITED STATES
upvote

Roberto commented on May 04, 2021
This is a good hack to pass the exam.
ITALY
upvote

LarBear commented on January 25, 2019
I have used brain dumps before and working great.
UNITED STATES
upvote

Adrian commented on August 11, 2018
The test engine is for windows only so does not work on my mac (I knew this before purchasing as they mention this on the website). The Android app crashes when I try to activate. I purchased from here because of the apps since I can get the pdf questions from several places on the web. Disappointed customer. Try somewhere else.
UNITED STATES
upvote

Life commented on June 22, 2018
Good CAPM questions AND GUIDE!
UNITED STATES
upvote