Through whom do project managers accomplish work?

  1. Consultants and stakeholders
  2. Stakeholders and functional managers
  3. Project team members and consultants
  4. Project team members and stakeholders

Answer(s): D



Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

  1. Checksheets
  2. Histograms
  3. Flowcharts
  4. Control charts

Answer(s): C



The following is a network diagram for a project.


The total float for the project is how many days?

  1. 5
  2. 9
  3. 12
  4. 14

Answer(s): B



The following is a network diagram for a project.

The free float for Activity E is how many days?

  1. 2
  2. 3
  3. 5
  4. 8

Answer(s): C



Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

  1. Smooth/accommodate
  2. Withdraw/avoid
  3. Compromise/reconcile
  4. Force/direct

Answer(s): B