The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
Answer(s): A
Process: 6.2 Define ActivitiesDefinition: The process of identifying and documenting the specific actions to be performed to produce the project deliverables.Key Benefit: The key benefit of this process is to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.Inputs1. Schedule management plan2. Scope baseline3. Enterprise environmental factors 4. Organizational process assetsTools & Techniques1. Decomposition2. Rolling wave planning3. Expert judgmentOutputs1. Activity list2. Activity attributes3. Milestone list
Which document includes the project scope, major deliverables, assumptions, and constraints?
Answer(s): B
The project team must complete a scope statement for developing a common understanding of the project scope among stakeholders. This lists project deliverables - summary level sub-products, whose full and satisfactory delivery marks the completion of the project.
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
7.2.2.4 Bottom-Up EstimatingBottom-up estimating is a method of estimating a component of work. The cost of individual work packages or activities is estimated to the greatest level of specified detail. The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purposes. The cost and accuracy of bottom-up cost estimating are typically influenced by the size and complexity of the individual activity or work package.
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
Answer(s): D
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
2.1.4 Organizational Process AssetsOrganizational process assets are the plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization. They include any artifact, practice, or knowledge from any or all of the organizations involved in the project that can be used to perform or govern the project. The process assets also include the organization’s knowledge bases such as lessons learned and historical information.Organizational process assets may include completed schedules, risk data, and earned value data. Organizational process assets are inputs to most planning processes. Throughout the project, the project team members may update and add to the organizational process assets as necessary. Organizational process assets may be grouped into two categories: (1) processes and procedures, and (2) corporate knowledge base.Process: 4.6. Close Project or PhaseDefinition: The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project.Key Benefit: The key benefit of this process is that it provides lessons learned, the formal ending of project work, and the release of organization resources to pursue new endeavors.Inputs1. Project management plan2. Accepted deliverables3. Organizational process assetsTools & Techniques1. Expert judgment2. Analytical techniques3. MeetingsOutputs1. Final product, service, or result transition2. Organizational process assets updates