Having worked in portfolio management before, you are pleased you were selected to implement it and be the portfolio manager for your motorcycle company, well known throughout the world. As it is a new function, you worked with the Enterprise Program Management Office to ensure you had a complete inventory of the work in progress. Now as you prepared your various portfolio management artifacts, and have a Portfolio Review Board meeting upcoming in two weeks, sponsors will be proposing new components. This means:

  1. A master schedule of resource allocation is needed
  2. The meeting also should focus on reviewing existing components to see if they are aligned with current strategy
  3. People throughout the organization should know about this meeting and its decisions
  4. The meeting should have a set agenda, and each member should be contacted before it to learn of key issues

Answer(s): A



Your executive management has been recently undergoing a change from a functional organization to a projectized one and is currently assessing the volume of work that the organization can execute. Which of the following tools and techniques will decide the volume of work and components that the organization can execute?

  1. Weighted Ranking and Scoring
  2. SWOT Analysis
  3. Capability and Capacity Analysis
  4. Quantitative & Qualitative Analysis

Answer(s): C



You are managing a large portfolio and are approaching to a major checkpoint. As a portfolio manager, you are now collecting information and reports from various components for aggregation and presentation. What method/tool can you use to support you in this process?

  1. Elicitation
  2. PMIS
  3. Manage Portfolio Information
  4. Communication methods

Answer(s): A



Ideally, the organization practices a policy of open communications on risks and encourages people to point any out at all levels, even if the risk does not affect one's own work and especially if it affects the portfolio. Different people, though, have different perspectives of the various portfolio risks based on their position in the organization. Assume a risk has been identified concerning the organization's operating model. This risk was identified by:

  1. A functional manager
  2. A PMO Director
  3. An executive
  4. The portfolio manager

Answer(s): C



Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. You are currently assessing risk against multiple criteria and classifying them as part of developing the risk management plan. Which of the below reflects what you are doing?

  1. Quantitative and Qualitative analysis
  2. Graphical Analytical methods
  3. Categorizing Risks
  4. Weighted Ranking and Scoring Techniques

Answer(s): D