Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, change to reflect the new stakeholders and their expectations?

  1. Communication Management Plan
  2. Portfolio Roadmap
  3. Portfolio Strategic Plan
  4. Portfolio Management Plan

Answer(s): A



Management practices are leveraged by organizational resources and as a portfolio manager, you realize that the correct management of supply and demand with relation to organizational resources is crucial to the success of a portfolio. Which of the following is not an organizational resource?

  1. Program and project managers
  2. None of the options
  3. Funds
  4. Assets

Answer(s): B



When we talk about portfolios, programs and projects, it is inevitable to mention the business value which is the sum of tangible and intangible assets of an organization, also known as the net quantifiable benefit.

When it comes to business value, at which level of the organization is the pursuit of Business Value optimized?

  1. Program
  2. Portfolio
  3. Operational
  4. Project

Answer(s): B



One of your goals as a portfolio manager is to ensure that your stakeholders receive the information they need for decision making. To help manage the portfolio information that is provided, you decide to gather information by holding portfolio component review meetings.
Your purpose in holding these meetings is to:

  1. Ensure the components can provide the data required for status reports
  2. Use them to introduce the portfolio management information system
  3. Validate data that now are in the reports
  4. Work with component managers to plan dashboard reports

Answer(s): C



In a portfolio, data is an abundant asset, and managing the information aiming for a a better decision making is critical. For this you use a variety of Quantitative and Qualitative analysis methods. These methods are performed in 4 of the portfolio management processes and serve a slightly different purpose in each and every one of them. Considering that you are currently performing risk assessment and handling risk responses, how can you make use of the quantitative and qualitative analysis?

  1. Performing resource leveling, project sequencing techniques and dependency analysis
  2. Performing Cost-benefit analysis, quantitative analysis, scenario analysis, probability analysis, SWOT analysis, Market/competitor analysis and business value analysis
  3. Performing Status and trend analysis, Rebalancing methods, Investment choice tools, exposure charts
  4. Performing Quantitative analysis and Sensitivity analysis

Answer(s): D