Managing risk is key to the success of any initiative. Risk is considered to be inherent in any activity we do in project management and at any level. Risk is part of project, program and portfolio management and has a different exposure in each and every one. Which of the following highlights this difference?
Answer(s): D
You have been receiving complaints from Key Stakeholders about multiple projects not being initiated, also they have great strategic alignment. What should have been done to avoid this?
As you grow older, you gain more experience and things that once seemed hard to assimilate, can become very easy. One junior member of your portfolio management team is confused on the relationship between the Optimize, Authorize and Provide Oversight processes. What could your advice to him be?
Answer(s): A
You have just recommended the Portfolio Strategic Plan and Portfolio to the governance board for approval. The portfolio board members informed you that they did not find what they were looking for in the strategic plan and that it needs to be reworked. What should have been part of your Strategic Plan?
As a portfolio manager you try to use all the information available to you in order to get the best out of the existing information and to better plan and manage the portfolio. The Enterprise Environmental Factors are important and referenced throughout the portfolio life cycle. Which of the following is correct regarding their purpose and focus?
Answer(s): C