Your sponsor has urged you to analyze Portfolio Risk before the end-of-week governance board meeting as the CEO will be present and is interested in Portfolio risk data in particular. Currently, you do not have adequate risk information in order to analyze data and give recommendations. Which tool is the most suitable for you to use in this case?

  1. Cumulative distribution
  2. Weighted Ranking and Scoring Techniques
  3. Delphi
  4. Graphical Analytical methods

Answer(s): C



Performance reporting is important in a program and usually, the portfolio manager aggregates performance information from the portfolio components in order to present the related reports. Which of the following measures can be used in performance reporting?

  1. Earned Value
  2. Cost Sunk
  3. All the options
  4. CPI and SPI

Answer(s): C



Recognizing that different components can have different types of risks, you decide to see how each risk affects the components. For example, assume you have identified a structural risk as overly ambitious plans and determine this risk affects three of the top five risks in your portfolio. You also have identified an environmental risk, in terms of whether the component will promote the organization's vision, which affects two components. Each component then has some other types of risks that affect it. From such an analysis you can see:

  1. Gaps in the portfolio
  2. Common causes
  3. Overall portfolio risk impact
  4. Rebalancing needs

Answer(s): B



A portfolio includes a lot of independent components with the same strategic aim. As a portfolio manager you will need to preare a qualified list of components to be used to reach the strategic goals and objectives. What input can you use in order to define the mix of portfolio components?

  1. Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Portfolio Process Assets, Portfolio
  2. Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter,Portfolio Process Assets, Portfolio Management Plan
  3. Portfolio Strategic Plan, Portfolio Management Plan, Portfolio Roadmap, Portfolio Charter,Portfolio Process Assets, Portfolio
  4. Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Portfolio Process Assets, Organizational Process Assets

Answer(s): C



The members of your Portfolio Review Board and other key stakeholders tend to be risk adverse as the company has survived recent recessions and is profitable. However, in an upcoming meeting with the corporate Board of Directors, they have asked you to show the frequency of meeting certain cost objectives at various percent points. For example assume the portfolio is to meet a $41,000 target in the next month, to be 75% confident this will occur, a forecast of $50,000 is needed. This means you need to show:

  1. The needed contingency reserve
  2. The probability of achieving portfolio objectives
  3. The confidence of meeting success criteria
  4. The values of KPIs with their confidence levels

Answer(s): B