Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

  1. RFI
  2. RFP
  3. RFQ
  4. IFB

Answer(s): A



If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

  1. .99
  2. -$2,500
  3. $2,500
  4. 1.02

Answer(s): C



Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

  1. Net present value
  2. Future value
  3. Present value
  4. Cost-Benefit ratio

Answer(s): A



Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

  1. Half float
  2. Full float
  3. Total float
  4. Free float

Answer(s): C,D