Free PGMP Exam Braindumps (page: 28)

Page 27 of 113

All of the following are resources that need to be monitored and controlled except for which one?

  1. Equipment
  2. Staff
  3. Quality
  4. Facilities

Answer(s): C



What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

  1. pert
  2. gert
  3. pmis
  4. Monte Carlo

Answer(s): D



All of the following are resources that you will need to monitor and control in a program environment except for which one?

  1. Staff members
  2. Contracts
  3. Quality
  4. Equipment

Answer(s): C



You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

  1. The local government
  2. The change control board
  3. The stakeholders
  4. The program board

Answer(s): D






Post your Comments and Discuss PMI PGMP exam with other Community members: