Which of the following represents the duration of activities against a calendar?

  1. Pie chart
  2. Scatter chart
  3. Gantt chart
  4. Pareto chart

Answer(s): C



is the degree to which a set of inherent characteristics fulfills requirements.

  1. Scope
  2. Project phase
  3. Regulation
  4. Quality

Answer(s): D



What does CPI value less than 1.0 indicates?

  1. Cost overrun for work completed
  2. Scheduled performance is great
  3. Cost underrun of performance to date
  4. Cost for completed work is as per estimate

Answer(s): A



When is the lessons learned document updated?

  1. At closing phase
  2. At planning phase
  3. Throughout the project lifecycle
  4. At execution phase

Answer(s): C



After program closure, the lessons learned document becomes the part of    ?

  1. The risk register
  2. The company's organizational process assets
  3. The program's performance record
  4. The program charter

Answer(s): B