A project manager in your program is using progress elaboration as part of their planning approach. This approach is also known as what planning methodology?

  1. Waterfall management
  2. Rolling wave planning
  3. Scope refinements
  4. Incremental planning

Answer(s): B



Who makes Go/No-Go decisions during phase gate reviews?

  1. Program Governance board
  2. Program Manager
  3. Board of Project Managers
  4. Stakeholders

Answer(s): A



Which of the following tools/techniques keep program managers and executives informed of the program's progress?

  1. Component analysis
  2. Expert judgment
  3. Review meetings
  4. Capacity planning

Answer(s): C



You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?

  1. Audit reports
  2. Program management plan
  3. Program performance reports
  4. Program issues register updates

Answer(s): D