You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

  1. .83
  2. -$20,000
  3. .91
  4. Negative ten percent

Answer(s): C



A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?

  1. Program risk register
  2. Program scope management plan
  3. Program risk management plan
  4. Component project risk register

Answer(s): B



An unforeseen geopolitical risk impacts a program to establish a company’s operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately, what appeared to be a significant risk resulted in a negligible risk.
What should the program manager recommend to stakeholders for future, similar situations?

  1. Accept the risk
  2. Seek an expert opinion
  3. Establish an on-call risk response team
  4. Review the risk severity matrix

Answer(s): A



A global financial system is being delivered by the program team to allow access from anywhere in the world. Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted to validate compliance with this new regulation. This event, which was not anticipated at this phase of the program, will generate additional work for the program team. This effort is not included in the current program roadmap and benefits delivery plan.
What immediate actions should the program manager take?

  1. Negotiate with the CEO in an attempt to avoid the audit
  2. De-scope the capabilities of the system to not allow access from abroad
  3. Accept the risk of the audit and continue the program as planned
  4. Assess the impact of the audit and potential remediation on the program

Answer(s): D



A program is completed and the expected benefits are realized.
Before executing the transition and closing of the program, what should the program manager do?

  1. Create a final program report to share with the stakeholder community
  2. Archive documents and lessons learned for future program references
  3. Obtain approval from the program governance board to initiate program closure activities
  4. Perform administrative and program management information system (PMIS) closure activities

Answer(s): B