The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

  1. Program management performance variances, business criteria reweighting, root cause identification, and statistical sampling.
  2. Interviewing, SWOT analysis, run chart, and matrix-based charts.
  3. Earned value management, financial reporting systems, performance measurement techniques, and program management information systems.
  4. Delphi technique, scatter diagram, Pareto chart, and organization charts.

Answer(s): C



A new program is comprised of four component projects. The program manager must assign project managers to each of the four projects. There are eight potential project managers to consider.
What should the program manager do before assigning the project managers?

  1. Determine budgetary constraints related to the project managers’ salaries
  2. Request performance feedback from the project managers’ line managers
  3. Evaluate the project managers’ skills and match them to the needs of the projects
  4. Interview each project manager to determine their career aspirations

Answer(s): C



The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.
Where is this expectation documented?

  1. Program quality standards
  2. Customer management plan
  3. Benefits management plan
  4. Benefits sustainment plan

Answer(s): A



A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board’s expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?

  1. Review the final program outcome with the program sponsor
  2. Prepare a program change request utilizing new board member input
  3. Review the strategic plan and benefits management plan with the board
  4. Present the final program status, costs, and schedule reports

Answer(s): C



A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program’s benefits sustainment and transition plan. What should the program manager do to create this plan?

  1. Identify key measures to compare expected benefits in the benefits management plan with actual performance once benefits sustainment and program transition starts.
  2. Assign creation of the benefits sustainment plan to the organization responsible for monitoring and controlling the sustainment period.
  3. Interview stakeholders, and revise the benefits management plan to provide new insight into the program’s execution and benefits sustainment period.
  4. Update the benefits management plan, and provide a copy to the organization responsible for measuring the sustainment period.

Answer(s): A