The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?
Answer(s): C
A new program is comprised of four component projects. The program manager must assign project managers to each of the four projects. There are eight potential project managers to consider.What should the program manager do before assigning the project managers?
The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.Where is this expectation documented?
Answer(s): A
A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board’s expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.How should the program manager handle this situation?
A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program’s benefits sustainment and transition plan. What should the program manager do to create this plan?