You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?

  1. $2,656,500
  2. There is not enough information to know.
  3. $3,795,000
  4. $1,035,000

Answer(s): C



June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?

  1. Program network diagram
  2. Program benefits mapping chart
  3. Program budget
  4. Program work breakdown structure

Answer(s): D



A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?

  1. .93
  2. .82
  3. $323,889
  4. -$38,889

Answer(s): A



What document should you provide to the vendors if you're only interested for a set fee for their materials?

  1. IFB
  2. RFP
  3. RFI
  4. SOW

Answer(s): A