PGMP Practice Test & Exam Dumps
Program Management Professional Questions 296–300 (page: 61)

Updated On: 10-Feb-2026

A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager’s next step?

  1. Assign project managers and resources
  2. Classify the program’s benefits
  3. Identify the program sponsor and program stakeholders
  4. Develop the program business case

Answer(s): B



A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project.
What should the program manager do next?

  1. Reassess the project manager’s credentials
  2. Assign a different project manager
  3. Review the skill requirements of the project
  4. Apply the competence assessment techniques to resolve the issue

Answer(s): C



A program manager concurrently implements a software program at four client locations. The client’s objective is to maintain quality while shortening the software implementation timeline.
What key elements should be included in the benefits register to achieve this goal?

  1. Plans for tracking and communicating risks associated with the program
  2. Plans for conducting program quality assurance and control on a regular basis
  3. Plans for program schedule control to meet the shorter timeline
  4. Plans for defining metrics and key performance indicators (KPIs), and procedures to measure benefits.

Answer(s): D



A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

  1. Certify contract completion
  2. Conduct a procurement audit to review the procurement process
  3. Assess all contracts to ensure all agreed conditions are met
  4. Review contract management plan for completeness

Answer(s): C



A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million.
Since the shutdown was not anticipated, what should the program manager do first?

  1. Implement the appropriate risk response plan and inform the stakeholders of the planned actions.
  2. Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.
  3. Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.
  4. Collaborate with the sponsor to determine options and negotiate a new date for the milestone.

Answer(s): C



Viewing page 61 of 126
Viewing questions 301 - 305 out of 713 questions


Post your Comments and Discuss PMI PGMP exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!