The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee.
What do the current findings show?

  1. Project C is running behind schedule and is over budget; projects A, B, and D are on schedule.
  2. Project A is running ahead of schedule and is under budget; projects B, C, and D are behind schedule.
  3. The overall program is performing within an acceptable level of variance.
  4. Project A is running behind schedule and is over budget; projects B, C, and D are on schedule.

Answer(s): D



A program manager learns that their company’s organizational strategy has changed. This change impacts one component project of a program, misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete.
What should the program manager do next?

  1. Immediately submit a component project closure request to the program sponsor so that resources can be reallocated to strategically aligned component projects.
  2. Assess the impact of closure on other component projects, and generate a recommendation for submission to the program governance board.
  3. Recommend that the component project manager complete work activity to deliver benefits to the organization.
  4. Update the benefits management plan to reflect the impact of the change on the program and its intended benefits.

Answer(s): B



An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback. As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.
What should the program manager do next?

  1. Document the results to share with the program governance board.
  2. Facilitate another test market sampling.
  3. Contact the R&D department for product testing results.
  4. Review the program management information system (PMIS) for lessons learned.

Answer(s): D



A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified.
Key stakeholders for the program should include which of the following?

  1. Potential customers, government regulatory agencies, and competitors
  2. Project management office (PMO), third-party contractors, and agents
  3. Local car dealers, factory workers, and corporate officers
  4. Vice president of logistics, potential customers, and corporate executives

Answer(s): A



An R&D group director approves a major program’s charter. Although the director has a high level of understanding of the program’s scope, they are unsure of how the program manager can be successful in delivering the program’s commitments.
What should the program manager do to align stakeholders with planning and monitoring the program’s progress?

  1. Establish high-level program milestones to achieve program benefits
  2. Develop an accountability matrix, and assign program roles and responsibilities
  3. Generate a supplier management plan to identify external stakeholders
  4. Create a communications management plan to achieve program benefits

Answer(s): A