A program management team is invited to a company’s annual strategy planning session. The CEO discusses the mission and vision of the organization, and how the strategic plan will create opportunities to fulfill them.
How can the program manager use the company’s vision to establish a program?

  1. Define the program and component projects to enable the fulfillment of strategic goals.
  2. Set the priority matrix, and map the projects’ priorities that will be included in the program.
  3. Define the program roadmap, and highlight the individual projects’ benefits.
  4. Identify program benefits that will enable the fulfillment of strategic goals.

Answer(s): A



Several issues are identified on one component project in a program. During a meeting with that component’s project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.
What should the program manager do?

  1. Join project-level issue resolution meetings to accelerate the decision-making process.
  2. Initiate discussions with the program governance board about assigning a more experienced project manager to the project.
  3. Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting.
  4. Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities.

Answer(s): A



A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals. A materials supplier informs the program manager that when this agreement is finalized, it will shorten the product’s delivery time.
What should the program manager update first?

  1. Procurement management plan
  2. Benefits register
  3. Risk register
  4. Benefits management plan

Answer(s): B



A program manager building the world’s largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?

  1. Finalize the business case and market analysis with the core program team and present the findings to the chief executive officer for approval.
  2. Work with the core program team to conduct a market analysis and make the decision based on the best return on investment.
  3. Arrange a meeting with both sponsors and the steering committee to present the market analysis and work through the conflict.
  4. Engage the program stakeholders, present the market analysis and findings to facilitate the decision on the best option.

Answer(s): D



A program with six projects has been running for three years. The company’s procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced.
The program manager will use the qualified seller list to do which of the following?

  1. Plan a proposal evaluation system
  2. Prepare the program procurement management plan
  3. Perform the required program budget updates
  4. Issue requests for proposals

Answer(s): D