PGMP Practice Test & Exam Dumps
Program Management Professional Questions 321–325 (page: 66)

Updated On: 10-Feb-2026

The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system’s cost. The program
manager has provided monthly performance reports throughout the program’s life cycle. Which of the following would the customer be interested in reviewing?

  1. Estimate to complete
  2. Estimate at completion
  3. Original cost baseline
  4. Cost performance index

Answer(s): D



A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager’s attempts to reach the stakeholder via email also fail.
What should the program manager do next?

  1. Escalate the issue to the stakeholder’s supervisor detailing the current situation
  2. Escalate the issue to the program governance board, as delays will impact the program
  3. Update the program risk register to reflect a realized risk and execute the documented risk response
  4. Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks

Answer(s): D



After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed. A strategic component project presents significant risk to organizational objectives due to its complexity and dependencies on external parties. After a series of board meetings, the enterprise’s investment committee approves a budget to implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility. Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?

  1. Share the concerns with the program sponsor to confirm understanding of the new development. Next, update the program budget, implementation plan, and risk management plan for governance board approval.
  2. Update the component project’s risk register, issue log, implementation plan, and risk management plan. Next, meet with the program sponsor to revise the program budget, implementation plan, and risk management plan for governance board approval.
  3. Revise the program budget, and implement the component project by managing it closely to recover the month-long delay. Next, update the component’s project and risk management plans for governance board approval.
  4. Update the program budget, and task the component project manager with implementing the plan. Next, submit a change order for approval to apply more resources to reduce the larger program’s risk profile.

Answer(s): B



Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company’s staff is unhappy about the acquisition. As a result, company B’s project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?

  1. Inform the stakeholders of this issue as soon as possible
  2. Change the program standards, aligning them with the project standards
  3. Work with the reports provided to extract the required information
  4. Remind the project manager of the relevant program standards

Answer(s): D



An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts, the program manager discovers the program may be shut down due to lack of funding.
To ensure continued funding for the program, what should the program manager do next?

  1. Complete the benefits sustainment plan and update the benefits register
  2. Present a revised ROI to the program sponsors based on the remaining investment
  3. Conduct a cost-benefit analysis to ensure the program sponsors understand the program’s long-term benefits
  4. Review the program business case and the program’s strategic alignment and long-term benefits with the program governance board

Answer(s): C



Viewing page 66 of 126
Viewing questions 326 - 330 out of 713 questions