A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?

  1. Program scope management plan
  2. Program governance plan
  3. Program scope statement
  4. Program work breakdown structure

Answer(s): C



A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?

  1. Update the program stakeholder engagement plan with stakeholders from the transition organization
  2. Define the component project’s business value in the benefits management plan
  3. Update the program roadmap to reflect completion of a key end-point objective
  4. Initiate a program change request to close out the component project

Answer(s): A



A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components’ strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the
issues identified is the lack of incorporation of both software and configuration management tools. Which of the following must be addressed?

  1. Program performance monitoring and controlling
  2. Program management information system (PMIS)
  3. Program delivery management
  4. Program roadmap

Answer(s): B



Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

  1. Decompose the program work based upon available resources
  2. Decompose the program to the work package level
  3. Decompose the program to the architecture baseline level
  4. Decompose the program at a level sufficient to achieve control

Answer(s): D



A small, regional utility closes a customer rewards program and transitions it to operations. The executive sponsor and program manager are concerned about the impact on benefits realization. The program manager assures the executive sponsor that any corrective actions will be included in the next phase.
What should the program manager do to ensure a successful transition?

  1. Ask each project manager to consolidate and file all program documentation in the corporate archives.
  2. Obtain all project manager’s contact information, and then have them reassigned back to their functional managers.
  3. Ask the program’s business analyst to collect all project information and create a report.
  4. Ensure that all program documents, including lessons learned, are archived in the knowledge repository.

Answer(s): D