Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal.
What should the agile team do?

  1. Create a central repository for information, and provide access to team B
  2. Use an information board that will be visible to all passing through the workspace
  3. Email all stakeholders with status updates
  4. Provide team B with the information on an ג€as neededג€ basis

Answer(s): B



Chart Base on the burn down chart, what is the iteration's status?

  1. It trended ahead of scheduled and completed everything on time
  2. It took more time than expected and had to be lengthened
  3. It trended behind schedule and did not complete everything on time
  4. It took less time than expected and had to be shortened

Answer(s): A



During planning sessions, an agile practitioner notices that some team members do not share common ideas.
What should the agile practitioner do?

  1. Ask the team if they would like to adopt alternative techniques
  2. Create a team norms document to set particular guidelines
  3. Ask the scrum master to resolve the issue at the stand up meeting
  4. Capture feedback during lessons learned at the end of the iteration

Answer(s): A



More details for a story are required before the upcoming sprint planning meeting.
What should the scrum master do?

  1. Email the product owner requesting detailed story specifications and wait for a response
  2. Gather the details from the team members before sprint planning
  3. Schedule a story grooming session with the product owner before sprint planning
  4. Conduct a planning poker session with the team

Answer(s): C