During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to efficiently complete its stories.
What should the team do?

  1. Cross-train some members in the automation framework to broaden their capacity with that skill
  2. Ask the product owner to add team members to boost this particular skill set
  3. Send a member to automation framework training when funds are available
  4. Avoid using test automation by swarming on the testing tasks and using manual testing

Answer(s): A



During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer.
How should the team resolve this?

  1. Refer to the values of the agile framework and the team
  2. Review the signed customer contract
  3. Check the sprint priority list
  4. Submit the problem to the product owner

Answer(s): D



A project team realizes that an important task on the iteration backlog will take more time than originally estimated.
What should the project team do?

  1. Continue working on the task until it is completed
  2. Remove the task owner from the project team
  3. Add resources to reduce time to task completion
  4. Stop working on the task and include it in the next iteration

Answer(s): D



An executive sponsor of a new scrum team actively attends scrum ceremonies.
How does this benefit the team?

  1. It helps the team to focus on and meet sprint goals
  2. It reminds the team about who sponsors the project
  3. It provides high-level project updates to the sponsor
  4. It helps to quickly resolve issues using the sponsor/s influence

Answer(s): D