When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts. What should the business analyst do?

  1. Negotiate for a quick approval of a reduced set of traceability artifacts.
  2. Explain the value of requirements traceability.
  3. Eliminate traceability activities for the project.
  4. Start development activities without traceability items.

Answer(s): A



A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

  1. Use cased
  2. Requirements management plan
  3. Traceability matrix
  4. Work breakdown structure

Answer(s): B



After implementation of the product, the customer reports defects. What is the best course of action to take?

  1. Escalate the issue to the project manager since the acceptance was given by the customer.
  2. Do nothing since the solution is now the responsibility of the operations manager.
  3. Compare reported defects with user acceptance test results.
  4. Involve the end users and plan a new round of acceptance tests to check the gaps.

Answer(s): C



A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume reporting required by the company’s financial department. The business analyst for the project determines that the selection criteria needed was not specified in the system requirements or design specifications.

Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement was missed?

  1. Root cause analysis, fishbone diagram, and/or the Five Whys
  2. Scope modeling, Ishikawa diagram, and/or the Five Whys
  3. Root cause analysis, problem tracking, and/or benchmarking
  4. Cause and effect diagram, brainstorming, and/or the Five Whys

Answer(s): C



A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch. The business analyst tells the stakeholder that the requirement status was changed to “deferred”.

What could have prevented the stakeholder from being surprised about the status change?

  1. The status should have been reviewed prior to project launch.
  2. The status should have been communicated to all project stakeholders.
  3. The status should have been updated in the traceability matrix.
  4. The status should have been communicated to the requirement’s source.

Answer(s): A