PMI PMI-RMP Exam Questions
PMI Risk Management Professional (Page 4 )

Updated On: 10-May-2026

A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the time, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization's risk appetite is low.

What is the first step that should be taken?

  1. Review the project schedule and recommend fast tracking the schedule and/or crashing the critical path.
  2. Discuss the project schedule with the executive sponsor and agree on a strategy for updating the risk management plan and risk response plans.
  3. Update existing risk response plans and include more resources to get the project back on track.
  4. Immediately call a steering committee meeting, report the project status, and suggest project scope reductions to save time.

Answer(s): B



During what process should a project manager assign a risk owner?

  1. Plan Risk Responses
  2. Plan Risk Management
  3. Monitor Risks
  4. Identify Risks

Answer(s): A



A risk manager wants to determine which risks are going to have the highest impact on a project.
Which of the following techniques should the risk manager use?

  1. Assumptions analysis
  2. Sensitivity analysis
  3. Root cause analysis
  4. Prioritization matrices

Answer(s): B



Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?

  1. Cross train others to reduce the SME workload.
  2. Introduce scope reductions to limit the reliance on SMEs.
  3. Replace the SME with resources, who are responsible for receiving output from the SME on their deliverables.
  4. Extend the project schedule timeline to accommodate availability of the SME.

Answer(s): B



In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?

  1. Evaluate the results of the Monte Carlo analysis
  2. Document and periodically update project risk information
  3. Monitor project metrics and performance information
  4. Update the risk management plan

Answer(s): C



The company board is concerned about potential legal action from a high-risk project What technique can be used to justify risk response decisions taken on this project?

  1. Interviews
  2. Nominal group technique
  3. Brainstorming
  4. Decision tree analysis

Answer(s): D



The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only.
Where would the project manager find the list of recipients for the report?

  1. Communications management plan
  2. Risk management plan
  3. Risk register
  4. Project charter

Answer(s): A



A CEO wants to reduce costs in the time spent for risk management activities.
What step did the risk manager fail to perform?

  1. Assigning the CEO as a risk owner
  2. Preventing all issues from occurring
  3. Properly communicating the risk management activities and their outcomes
  4. Explaining the purpose of the management reserve

Answer(s): B



Viewing page 4 of 59
Viewing questions 25 - 32 out of 463 questions


PMI-RMP Exam Discussions & Posts (Share your experience with others)

AI Tutor AI Tutor 👋 I’m here to help!