Free PMI-SP Exam Braindumps
PMI-SP PMI Scheduling Professional Questions 81–85 (page: 18)

Updated On: 10-Feb-2026

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

  1. Communications bull's eye
  2. Performance goals
  3. Earned value management goals
  4. Project exception report

Answer(s): A

Explanation:

The graphic shown in the figure is a communications bull's eye. The project manager must keep the project within the boundaries defined by the bull's eye or he will need to generate a performance report. This is an example of management by exception because the project manager only communicates with management when there is an exception, or variance, within the project.
Answer options C, B, and D are incorrect. These are not valid terms for the communications bull's eye.



Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases.
Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

  1. Quality inspections and compliance
  2. Location, logistics, and resource availability analysis
  3. Labor productivity studies from previous similar projects in the area
  4. The average price of general labor in the area

Answer(s): B,C,D

Explanation:

Constructability analysis takes into account the location, logistics, resource availability analysis, the average price of general labor in the area, and labor productivity studies from previous similar projects in the area. Constructability analysis is a process that starts in the initial planning phases and persists all over the entire planning cycle and into the implementation phase of the project. Constructability analysis during the planning process examines the methods and cost of installed equipment and materials, technology, site conditions, resources, and related infrastructure. The benefit of constructability analysis is to reduce both the time and cost of a project. Constructability analysis is repeatedly performed throughout the life-cycle of a project in order to optimize cost, plan, and schedule while mitigating risk. It is a very important process that needs to be performed early in planning to allow alternatives to be considered and integrated into the design.
Answer option A is incorrect. This comes under the quality assurance phase.



You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

  1. Direct expense
  2. External requirement
  3. Temporary resource
  4. Expert judgment

Answer(s): D

Explanation:

The consultant is an example of expert judgment, as he is helping you and the project team to create the project elements. Expert judgment is a technique based on a set of criteria that has been acquired in a specific knowledge area or product area. It is obtained when the project manager or project team requires specialized knowledge that they do not possess. Expert judgment involves people most familiar with the work of creating estimates. Preferably, the project team member who will be doing the task should complete the estimates. Expert judgment is applied when performing administrative closure activities, and experts should ensure the project or phase closure is performed to the appropriate standards.
Answer option A is incorrect. The consultant may be considered a direct expense because the fees can only be assigned to your project work, but this is not the best choice for the question.
Answer option B is incorrect. An external requirement is not a valid choice for this question.
Answer option C is incorrect. A temporary resource is not a valid project management term.



Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week.
What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

  1. Constraint
  2. Assumption
  3. Execution variance analysis
  4. Resource leveling heuristic

Answer(s): A,D

Explanation:

Resource leveling is a rule of limiting the total number of hours a project team may work during a given time period in the project. If management restricts the project work to 45 per week, as in this example, Holly's schedule will likely increase because the project team can't complete as much work in one given time period. While this may be seen as a constraint, because it limits Holly's options, it's technically called a resource leveling heuristic.
Answer option B is incorrect. It is an assumption that's believed to be true, but it hasn't been proven to be true.
Answer option C is incorrect. Execution variance analysis describes the difference between what was planned and what was executed. A better term for this experience would simply be a scope variance, scope change, or defect.



You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is.
What value do you report?

  1. -$135,000
  2. .67
  3. .81
  4. -$65,000

Answer(s): C

Explanation:

Cost performance index (CPI) is used to calculate performance efficiencies. It is used in trend analysis to predict future performance. CPI is the ratio of earned value to actual cost. The CPI is calculated based on the following formula: CPI = Earned Value (EV) / Actual Cost (AC) If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The CPI value of 1 indicates that the project is right on target. In this instances it is $270,000 divided by $335,000 for a CPI of .81.
Answer option B is incorrect. .67 is actually the schedule performance index.
Answer option D is incorrect. -$65,000 is the cost variance for the project.
Answer option A is incorrect. -$135,000 is the schedule variance of the project.



Viewing page 18 of 67
Viewing questions 86 - 90 out of 326 questions


Post your Comments and Discuss PMI PMI-SP exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!