You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G . How much float is available for Activity G to help offset the risk event?
Answer(s): D
There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float available for Activity G because it is on the critical path.
Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?
Answer(s): B
Rolling wave planning is a technique to plan and do the most imminent project work before moving onto the details that are far off in the project schedule and project plan. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period. Answer option D is incorrect. Decomposition is the process of breaking down work packages into the activity list. Answer options A and C are incorrect. These are not valid project management terms.
Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?
Answer(s): C
According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope baseline.A Work Breakdown Structure (WBS) in project management is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Answer option A is incorrect. The scope baseline is an input to define the project activities. Answer option D is incorrect. Enterprise environmental factors are an input to define the project activities. Answer option B is incorrect. Organizational process assets are an input to define the project activities.
You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?
Total float is the time you can delay an activity without delaying the project end date, whereas free float is on each activity and does not affect the early start date of successor activities. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayedfrom its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique. Answer options C, A, and D are incorrect. These are not accurate definitions of free float and total float.
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
Answer(s): A
The path of ABEHJ will take 22 days to complete and cannot exceed 28 days or else the project will be late. If Activity B takes four additional days and Activity E takes two additional days, this adds (4+2= 6) six days to the path, bringing the path's duration to exactly (22+6 = 28) days. There is no available float left for Activity D or H. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project fish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, C, and D are incorrect. There is no float available because the path's duration has increased to 28 days.
Post your Comments and Discuss PMI PMI-SP exam dumps with other Community members:
Anonny Commented on July 31, 2025 Will check after I complete Anonymous
Cindy Commented on July 31, 2025 SC-401 was definitely one of the tougher exams I’ve taken. The premium version of this exam dumps pdf exam dumps pdf really helped me pass. EUROPEAN UNION
Anonymous Commented on July 31, 2025 Helpful and realistic question exam dumps pdf for preparing for PSM1 exam. HONG KONG
yash Commented on July 31, 2025 this is nice set of questions which help on getting your topic understand more clearly Anonymous
LMB Commented on July 31, 2025 Question 55 is: NO YES YES GERMANY
Sanjay Commented on July 31, 2025 Awesome exam dump. Helped in the passing the exam Anonymous
Sanjay Commented on July 31, 2025 THis is awesome exam dump. It matched most of the questions in the exam Anonymous
G Commented on July 31, 2025 Most of the answers here are accurate AUSTRALIA
G Commented on July 31, 2025 Very helpful exam dumps pdf for higher success rates AUSTRALIA
pooja Commented on July 31, 2025 I am reading these questions and found them really helpful to understand . Anonymous
Pooja Commented on July 31, 2025 Very nice set of questions for preparation of AZ-104 Anonymous
Den Commented on July 30, 2025 answers have explanation which really helps to understand the topic Anonymous
Paul Commented on July 30, 2025 #115: the correct answer is D: Set field values and add messages. A Business Rule requires scripting to generate an event, so answer B is incorrect. UNITED STATES