Free PMI PMP Exam Braindumps (page: 39)

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours. The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.
What should the project lead have done initially to avoid this situation?

  1. Involved operations stakeholders during planning
  2. Reviewed the project management plan
  3. Increased support hours for the hours of operation
  4. Created a detailed operations manual

Answer(s): A



A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production. One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?

  1. Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities
  2. Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides
  3. Foster stakeholder participation by engaging them early on the backlog discussions
  4. Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress

Answer(s): A



After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work
(SOW). These changes would improve the project outcome.
What should the project manager do next?

  1. Consult the list of selected vendors for the bid and evaluate a possible change of vendor.
  2. Revise the procurement control process to avoid undesired changes that might affect the schedule.
  3. Assess the situation as an opportunity for improvement and perform a risk analysis.
  4. Conduct an audit on the procurement process and inform the vendor about the audit's observations.

Answer(s): C



A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?

  1. The project is earning less value than was planned
  2. The project has started exceeding the planned cost
  3. The project has earned more value than planned
  4. The project is close to exceeding the planned cost

Answer(s): B



Viewing page 39 of 356
Viewing questions 153 - 156 out of 1417 questions



Post your Comments and Discuss PMI PMP exam prep with other Community members:

PMP Exam Discussions & Posts