In an agile team, some of the team members are coming forward to ask for more autonomy on the project.
What should the project manager do in this situation?

  1. Encourage the team lead to make decisions.
  2. Encourage the team members to make decisions.
  3. Discourage them as conflicts may be created.
  4. Discourage this request, as it is for the management team.

Answer(s): B



A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?

  1. Meet with the team members and ask them how to spend the reward.
  2. Arrange a luncheon for all team members and include team-building sessions.
  3. Draft a points system to allocate a portion of the money for each resource.
  4. Allocate the reward to the team leaders to spend on the team as they see fit.

Answer(s): A



A company is conducting a digital transformation project that has a hard deadline. The marketing team wants to combine this implementation with a new product, and the newly assigned project manager is not aware of all the dependencies.
Using a hybrid approach, what should the project manager do to ensure the dependencies are taken into consideration?

  1. Implement a project newsletter so the different team members can be informed about the progress of each project.
  2. Make sure that each individual project schedule is aligned with the common deadlines.
  3. Combine all of the small projects into one big project so the team can collaborate better as one big team.
  4. Facilitate communication promoting a Scrum of Scrums so the different teams are aware of the dependencies and progress.

Answer(s): D



During an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog.
What should the project manager do next?

  1. Reevaluate the backlog priority with the product owner since the velocity has been impacted.
  2. Reevaluate the scope of the current iteration to keep the same velocity and timeline.
  3. Reevaluate the velocity as the iteration duration will be impacted by new requirements.
  4. Reevaluate the project schedule as the velocity will be impacted by the loss of resources.

Answer(s): A