Free RMP Exam Braindumps (page: 17)

Page 17 of 111

Lisa is the project manager of the FKN project for her organization. She is working with Sam, the CIO, to discuss a discount the vendor has offered the project based on the amount of materials that is ordered. Lisa and Sam review the offer and agree that while their project may qualify for the discounted materials the savings is nominal and they would not necessarily pursue the savings. Lisa documents this positive risk response in the risk register. What risk response is this?

  1. Enhance
  2. Transference
  3. Share
  4. Acceptance

Answer(s): D



You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the project's cost management plan. Why is it necessary to include the project's cost management plan in the preparation for the quantitative risk analysis process?

  1. The project's cost management plan can help you to determine what the total cost of the project is allowed to be.
  2. The project's cost management plan provides direction on how costs may be changed due to identified risks.
  3. The project's cost management plan provides control that may help determine the structure for quantitative analysis of the budget.
  4. The project's cost management plan is not an input to the quantitative risk analysis process.

Answer(s): C



You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What should you do with these identified risk events?

  1. All risks must have a valid, documented risk response.
  2. These risks can be accepted.
  3. These risks can be added to a low priority risk watch list.
  4. These risks can be dismissed.

Answer(s): C



You are the project manager of a new project in your organization. You and the project team have identified the project risks, completed risk analysis, and are planning the most appropriate risk responses. Which of the following tools is most effective to choose the most appropriate risk response?

  1. Cause-and-effect diagrams
  2. Project network diagrams
  3. Delphi Technique
  4. Decision tree analysis

Answer(s): D



Page 17 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote