Gary is the project manager of his organization. He is managing a project that is similar to a project his organization completed recently. Gary has decided that he will use the information from the past project to help him and the project team to identify the risks that may be present in the project. Management agrees that this checklist approach is ideal and will save time in the project. Which of the following statement is most accurate about the limitations of the checklist analysis approach for Gary?

  1. The checklist analysis approach is fast but it is impossible to build and exhaustive checklist.
  2. The checklist analysis approach saves time, but can cost more.
  3. The checklist analysis approach only uses qualitative analysis.
  4. The checklist is also known as top down risk assessment.

Answer(s): A



You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?

  1. Risk potential responses
  2. Risk schedule
  3. Risk owner
  4. Risk cost

Answer(s): A



You are the project manager for the TTR project. You are in the process of gathering information for risk identification. You ask experts to participate in the process through their emails for maintaining anonymity. You collect the responses, summarize them, and are then re-circulated to the experts for further comment. Which of the following techniques are you using for risk identification?

  1. Delphi
  2. Expert judgment
  3. SWOT analysis
  4. Brainstorming

Answer(s): A



Ben is the project manager of the CMH Project for his organization. He has identified a risk that has a low probability of happening, but the impact of the risk event could save the project and the organization with a significant amount of capital. Ben assigns Laura to the risk event and instructs her to research the time, cost, and method to improve the probability of the positive risk event. Ben then communicates the risk event and response to management. What risk response has been used here?

  1. Sharing
  2. Transference
  3. Enhance
  4. Exploit

Answer(s): C



Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat even once it will delay the project's end date. You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down. The temperature of 430 is called what?

  1. Risk response
  2. Risk event
  3. Risk trigger
  4. Risk identification

Answer(s): C