A high-profile, high-priority project within your organization is being created. Management wants you to pay special attention to the project risks and do all that you can to ensure that all of the risks are identified early in the project. Management has to ensure that this project succeeds. Management's risk aversion in this project is associated with what term?

  1. Quantitative risk analysis
  2. Risk conscience
  3. Risk mitigation
  4. Utility function

Answer(s): D



You are the project manager of the BJA Project for your company. Management is worried about one of the identified risks in your project. The risk event has a probability of 90 percent and a cost impact of $85,000. Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?

  1. Avoidance
  2. Acceptance
  3. Exploit
  4. Mitigation

Answer(s): D



Ben is the project manager of the YHT Project for his company. Alice, one of his team members, is confused about when project risks will happen in the project. Which one of the following statements is the most accurate about when project risk happens?

  1. Project risk can happen at any moment.
  2. Project risk happens throughout the project execution.
  3. Project risk is always in the future.
  4. Project risk is uncertain, so no one can predict when the event will happen.

Answer(s): C



There are seven risk responses, a project manager can use to address risk events. Which one of the following is a risk response that is appropriate for positive or negative risk events depending on the scenario in the project?

  1. Avoidance
  2. Acceptance
  3. Sharing
  4. Transference

Answer(s): B



You are the project manager of the NHQ Project for your company. You are discussing some of the project issues that need to be resolved in the project. You and the project stakeholders come to an agreement about the risk issues and how they will be resolved. Where should you document this information for issue resolution?

  1. Project management plan for execution
  2. Lessons learned documentation
  3. Issue log
  4. Risk response plan

Answer(s): C