PMI RMP Exam
PMI Risk Management Professional Exam (Page 31 )

Updated On: 1-Feb-2026

You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.

  1. List of mitigation techniques
  2. List of key stakeholders
  3. List of identified risks
  4. List of potential responses

Answer(s): C,D



Kelly is the project manager of the NNQ Project for her company. This project will last for one year and has a budget of $350,000. Kelly is working with her project team and subject matter experts to begin the risk response planning process. When the project manager begins the plan risk response process, what two inputs will she need?

  1. Risk register and the risk response plan
  2. Risk register and power to assign risk responses
  3. Risk register and the risk management plan
  4. Risk register and the results of risk analysis

Answer(s): C



John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk?

  1. Activity duration estimates
  2. Schedule management plan
  3. Risk management plan
  4. Activity cost estimates

Answer(s): A



Your project is an agricultural-based project that deals with plant irrigation systems. You have discovered a byproduct in your project that your organization could use to make a profit. If your organization seizes this opportunity it would be an example of what risk response?

  1. Enhancing
  2. Opportunistic
  3. Positive
  4. Exploiting

Answer(s): D



You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?

  1. Probabilistic analysis of the project
  2. Probability of achieving cost and time objectives
  3. Risk distributions within the project schedule
  4. Trends in quantitative risk analysis

Answer(s): C



Viewing page 31 of 90
Viewing questions 151 - 155 out of 273 questions



Post your Comments and Discuss PMI RMP exam prep with other Community members:

Join the RMP Discussion