Free RMP Exam Braindumps
PMI Risk Management Professional Exam Questions 176–180 (page: 37)

Updated On: 10-Feb-2026

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?

  1. Risk register
  2. Risk log
  3. Risk management plan
  4. Project management plan

Answer(s): A



You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?

  1. Change request log
  2. Lessons learned
  3. Project archives
  4. Project document updates

Answer(s): A



You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the quantitative risk analysis process?

  1. Probability of reaching project objectives
  2. Risk register updates
  3. Risk response
  4. Risk contingency reserve

Answer(s): B



Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders – including management. Mark will need to update all of the following information except for which one?

  1. Prioritized list of quantified risks
  2. Watchlist of low-priority risks
  3. Trends in qualitative risk analysis
  4. Risks grouped by categories

Answer(s): A



The risk transference is referred to the transfer of risks to a third party, usually for a fee, it creates a contractual-relationship for the third party to manage the risk on behalf of the performing organization. Which one of the following is NOT an example of the transference risk response?

  1. Use of insurance
  2. Warranties
  3. Life cycle costing
  4. Performance bonds

Answer(s): C



Viewing page 37 of 90
Viewing questions 181 - 185 out of 273 questions


Post your Comments and Discuss PMI RMP exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!