Free RMP Exam Braindumps (page: 36)

Page 36 of 111

You are the project manager of the HQQ Project for your company. You are working with your project stakeholders to discuss the risks in the project that can adversely affect the project objectives. You are discussing the possibilities of causes for an identified risk event in your project. Your stakeholder is confused on the difference between causes and risk events. Which of the following is NOT an example of a cause for a project risk?

  1. Limited team members to complete the project work
  2. Quality assurance programs within the company
  3. Work permit requirements
  4. Schedule constraints on the project

Answer(s): B



Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?

  1. -$217,500
  2. 20 percent
  3. -$174,000
  4. -$269,000

Answer(s): C



You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management approved, was to increase the project schedule because there was risk surrounding the installation time of a new material. Your logic was that with the expanded schedule there would be time to complete the installation without affecting downstream project activities. What type of risk response is being audited in this scenario?

  1. Parkinson's Law
  2. Mitigation
  3. Avoidance
  4. Lag Time

Answer(s): C



Gary is the project manager for his organization. He is working with the project stakeholders on the project requirements and how risks may affect their project. One of the stakeholders is confused about what constitutes risks in the project. Which of the following is the most accurate definition of a project risk?

  1. It is an uncertain event that can affect the project costs.
  2. It is an uncertain event or condition within the project execution.
  3. It is an uncertain event that can affect at least one project objective.
  4. It is an unknown event that can affect the project scope.

Answer(s): C



Page 36 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote