Free RMP Exam Braindumps (page: 40)

Page 40 of 111

You are the project manager of a large construction project. You are evaluating the strengths, weaknesses, opportunities, and threats involved in a project. In which of the following processes are you on?

  1. Define Scope
  2. Plan Risk Responses
  3. Plan Risk Management
  4. Identify Risks

Answer(s): D



You are the project manager of the NHQ project for your company. Management has told you that you must implement an agreed upon contingency response if the Cost Performance Index in your project is less than 0.90. Consider that your project has a budget at completion of $250,000 and is 60 percent complete. You are scheduled to be however, 75 percent complete, and you have spent $165,000 to date. What is the Cost Performance Index for this project to determine if the contingency response should happen?

  1. -$37,500
  2. 0.91
  3. 0.88
  4. 0.80

Answer(s): B



Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to the plan risk management process. Which one of the following is NOT an input to this process?

  1. Project scope statement
  2. Risk management plan
  3. Schedule management plan
  4. Cost management plan

Answer(s): B



Which of the following are parts of SWOT Analysis? Each correct answer represents a complete solution. Choose all that apply.

  1. Opportunities
  2. Tools
  3. Weaknesses
  4. Threats
  5. Strengths
  6. Optimism

Answer(s): A,C,D,E



Page 40 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote