Free RMP Exam Braindumps (page: 45)

Page 45 of 111

You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?

  1. Change request log
  2. Lessons learned
  3. Project archives
  4. Project document updates

Answer(s): A



You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the quantitative risk analysis process?

  1. Probability of reaching project objectives
  2. Risk register updates
  3. Risk response
  4. Risk contingency reserve

Answer(s): B



Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders – including management. Mark will need to update all of the following information except for which one?

  1. Prioritized list of quantified risks
  2. Watchlist of low-priority risks
  3. Trends in qualitative risk analysis
  4. Risks grouped by categories

Answer(s): A



The risk transference is referred to the transfer of risks to a third party, usually for a fee, it creates a contractual-relationship for the third party to manage the risk on behalf of the performing organization. Which one of the following is NOT an example of the transference risk response?

  1. Use of insurance
  2. Warranties
  3. Life cycle costing
  4. Performance bonds

Answer(s): C



Page 45 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote