You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?
Answer(s): A
You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the quantitative risk analysis process?
Answer(s): B
Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders – including management. Mark will need to update all of the following information except for which one?
The risk transference is referred to the transfer of risks to a third party, usually for a fee, it creates a contractual-relationship for the third party to manage the risk on behalf of the performing organization. Which one of the following is NOT an example of the transference risk response?
Answer(s): C
Post your Comments and Discuss PMI RMP exam with other Community members:
Doroze commented on August 04, 2024 I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass. Anonymous upvote
Our website is free, but we have to fight against bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the RMP content, but please register or login to continue.