David is the project manager of the NKL Project for his organization. He has been asked to create a proposal for a construction project for a client. David realizes that there are several requirements within the SOW and RFP provided by the client that would eliminate his company from bidding on the construction project. David proposed to management that his organization create a partnership with a competitor so that together they could bid on the construction project and qualify for the customer's requirements. What risk response is David proposing to management?
Answer(s): D
Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?
Answer(s): C
Which of the following risk responses delineates that the project plan will not be changed to deal with the risk?
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?
Post your Comments and Discuss PMI RMP exam with other Community members:
Doroze commented on August 04, 2024 I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass. Anonymous upvote
Our website is free, but we have to fight against bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the RMP content, but please register or login to continue.