Free RMP Exam Braindumps
PMI Risk Management Professional Exam Questions 226–230 (page: 47)

Updated On: 10-Feb-2026

Diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana and the project team decided, along with the key stakeholders, to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?

  1. It is a risk event that is generated due to errors or omission in the project work.
  2. It is a risk event that is created by a risk response.
  3. It is a risk event that only has a negative side, such as loss of life or limb.
  4. It is a risk event that cannot be avoided because of the order of the work.

Answer(s): C



Management has asked you to perform a risk audit and report back on the results. Bonny, a project team member asks you what a risk audit is. What do you tell Bonny?

  1. A risk audit is a review of all the risks that have yet to occur and what their probability of happening are.
  2. A risk audit is a review of the effectiveness of the risk responses in dealing with identified risks and their root causes, as well as the effectiveness of the risk management process.
  3. A risk audit is a review of all the risk probability and impact for the risks, which are still present in the project but which have not yet occurred.
  4. A risk audit is an audit of all the risks that have occurred in the project and what their true impact on cost and time has been.

Answer(s): B



Consider the risk probability-impact matrix in the figure given below:


If Risk B happens in this project, how much will be left in the contingency reserve?

  1. $193,500
  2. -$334,500
  3. It depends on the total budget of the project.
  4. $148,300

Answer(s): A



Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?

  1. Brainstorming
  2. Delphi Techniques
  3. Checklist analysis
  4. Expert judgment

Answer(s): A



Mike is the project manager of the NNP Project for his organization. He is working with his project team to plan the risk responses for the NNP Project. Mike would like the project team to work together on establishing risk thresholds in the project. What is the purpose of a risk threshold?

  1. It helps to identify those risks for which specific responses are needed.
  2. It is a limit of the funds that can be assigned to risk events.
  3. It is a warning sign that a risk event is going to happen.
  4. It is a study of the organization's risk tolerance.

Answer(s): D



Viewing page 47 of 90
Viewing questions 231 - 235 out of 273 questions


Post your Comments and Discuss PMI RMP exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!