Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Risk management procedure heading?

  1. When a new problem arises, a full impact analysis will be undertaken to assess the impact on the project' objectives and Business Case.
  2. Probability will be assessed against the scales defined in this Risk Management Strategy.
  3. Any risk which has an expected value of more than £1 k will NOT be registered.
  4. Every threat and opportunity identified must be clearly defined in terms of cause, event and effect.
  5. 'Reduce' Response actions which result in a lower impact and/or probability rating.

Answer(s): B,D

Explanation:

The correct answers identify key risk management process requirements: B) Probability is assessed against the scales defined in the Risk Management Strategy, ensuring consistency and alignment with the project’s risk appetite; D) Every threat and opportunity identified must be clearly defined in terms of cause, event and effect, to enable analysis and response. A is incorrect because full impact analysis is not automatically triggered for every new problem; risk management uses initial risk assessment and ongoing monitoring per the strategy. C is incorrect as there is no preset monetary threshold that excludes risks from registration. E is incorrect because “Reduce” is a valid risk response option, but the statement misstates its effect on probability/impact.



Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under either the Records or Reporting headings?

  1. Project Support will maintain the Risk Register.
  2. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report.
  3. The Change Authority will report monthly to the Project Manager on the status of the change budget.
  4. Risks that are likely to occur within the next two weeks should be recorded as imminent.
  5. A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board.

Answer(s): B,C

Explanation:

The correct answer identifies ongoing risk assessment and control information appropriate for Records or Reporting.
A) Incorrect: Project Support maintaining the Risk Register is a role/activity, but the question asks what should be recorded under Records or Reporting headings, not who maintains it.
B) Correct: The evaluated net effect of all risks is summary information used for End Stage reporting; updating at end of each stage aligns with PRINCE2 governance and highlights overall risk exposure in the End Stage Report.
C) Incorrect: Change budget reporting is a Change Authority activity, not a standard Records/Reporting item for risks.
D) Incorrect: Imminent is a timing term for risk logging, but Records/Reporting guidance requires categorization rather than a timing label.
E) Incorrect: Highlight Reports summarize project health, not a consolidated risks summary; risks are typically in the Risk Register and End Stage Report.



Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Timing of risk management activities heading?

  1. During stage 4, the selected service provider will manage any risks to their Business Case and report these to the Project Manager on a weekly basis.
  2. The Project Board should hold monthly meetings to review project progress.
  3. When closing a project, the follow-on action recommendations should be updated with any risks relating to the realization of benefits after the outsourced services go live.
  4. Any new risks identified during product development should be reported to the Project Manager by the Team Manager when delivering the completed Work Package.
  5. When authorizing a stage, the Project Board will check that the exposure to risk is still acceptable.

Answer(s): B,E

Explanation:

The two correct statements align with ongoing risk management timing: B ensures governance oversight of risk exposure and progress at a suitable cadence, while E confirms risk exposure is re-assessed when authorizing a stage.
A is incorrect because stage 4 activity is not the defined timing for risk management within the current stage boundaries, and weekly reporting by a supplier is not a PRINCE2 risk timing requirement.
C is incorrect because closing a project and updating follow-on actions pertains to benefits realisation, not the ongoing timing of risk management activities.
D is incorrect because risk reporting by the Team Manager on delivering a Work Package relates to incident communication, not the formal timing of risk management activities.
E) correct: re-check exposure at stage authorization.
B) correct: regular Project Board review of risk and progress.



Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Roles and responsibilities heading?

  1. Each risk will be assigned a risk owner.
  2. Risks exceeding the agreed project risk tolerance will be reported to the Project Board.
  3. Risk tolerances are allocated to each stage by the Project Manager.
  4. Project Assurance will ensure that project risks are identified, assessed and controlled according to the agreed risk management procedure.
  5. An external consultant is to facilitate a risk identification workshop.

Answer(s): B,D

Explanation:

The correct statements align with Roles and responsibilities in PRINCE2 risk management: B and D.
A) Incorrect: assigning a risk owner is a risk management activity, but “Roles and responsibilities” heading seeks who manages risk reporting and assurance, not necessarily ownership for every risk.
B) Correct: risks exceeding the agreed risk tolerance must be escalated/report to the Project Board per risk management procedures.
C) Incorrect: risk tolerances are allocated to stages by the Project Board, not the Project Manager.
D) Correct: Project Assurance is responsible for ensuring risk management follows the procedure and is effective.
E) Incorrect: external facilitation is not mandated by Roles and responsibilities in this context.



HOTSPOT

Additional Information

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

  1. See Explanation for the Answer.

Answer(s): A

Explanation:



Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Proximity heading?

  1. Proximity categories for this project are: Imminent; Within the stage; Within the project; Beyond the project.
  2. The risk of MFH having no outsourcing experience will be categorized as Stage 4 proximity.
  3. Imminent risks are those which may occur within two weeks.
  4. Any risk with a proximity category of imminent will be estimated as having a very high impact.
  5. The risk of staff leaving the organization will be categorized as beyond the project proximity.

Answer(s): C,D

Explanation:

The correct statements identify timing-based proximity concepts: imminent risks relate to near-term events (C) and estimation of imminent risks should be at very high impact due to near-term consequences (D).
A) Incorrect — proximity categories are not presented as “Imminent; Within the stage; Within the project; Beyond the project” for this context.
B) Incorrect — proximity for a risk about outsourcing experience is not a Stage 4 categorization in PRINCE2 terms.
E) Incorrect — “beyond the project” proximity would apply to long-term, not near-term, threats like staff leaving in this scenario.
C) Correct — imminent implies events may occur within a short horizon, affecting timing.
D) Correct — imminent risks are typically assessed with high or very high impact due to near-term exposure.



Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Risk tolerance heading?

  1. Corporate management's threshold level of risk exposure is any combination of high and very high impact and probability.
  2. The Project Board's threshold level of risk exposure is any combination of medium, high and very high impact, with high and very high probability.
  3. The Project Manager's threshold level of risk exposure is low impact and probability.
  4. The cost of all fallback plans must be contained within the project's tolerance.
  5. The risk budget will have a tolerance of +/~ 10%.

Answer(s): B,D

Explanation:

The correct answer is B and D.
B) Reflects the Project Board’s risk tolerance: they determine acceptable exposure by combining medium, high, and very high impact with high or very high probability, aligning tolerance with governance for strategic risks.
D) States that fallback plan costs must be within the project’s tolerance, ensuring cost containment within defined risk responses and budgetary limits.
A) Incorrect: Corporate management thresholds are not used for project risk tolerance unless delegated; thresholds at corporate level do not define project tolerance.
C) Incorrect: Project Manager’s tolerance would be more specific to the project’s risk exposure, not simply low impact/probability, which is too restrictive for typical risk scenarios.
E) Incorrect: Risk budget tolerance is not universally fixed at +/- 10% unless defined; this is not a generic Project risk tolerance statement.



HOTSPOT

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Column 1 contains a number of risk responses identified by the Project Manager following an assessment of this risk. Column 2 contains a list of threat response types. For each risk response in Column 1, select from Column 2 the type of response it represents. Each option from Column 2 can be used once, more than once or not at all.

Column 1 contains a number of possible risk responses to the above risk. For each risk response, select from Column 2 the appropriate risk threat response type that it represents. Each selection from Column 2 can be used once, more than once or not at all.

  1. See Explanation for the Answer.

Answer(s): A

Explanation:

1 ­ Accept

2 ­ Fallback

3 ­ Share

4 ­ Accept

5 ­ Fallback

6 - Avoid



Viewing page 18 of 38
Viewing questions 137 - 144 out of 293 questions