PRINCE2 Practitioner (7th Edition) Questions 113–120 (page: 16)

Updated On: 21-Apr-2026

Which management product defines the detailed nature, purpose and function of a product?

  1. Plan
  2. Quality Register
  3. Project Product Description
  4. Product Description

Answer(s): D



HOTSPOT (Drag and Drop is not Supported)

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)



Extract from Stage Plan for stage 3.




(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Product Summary and Product Breakdown Structure provided as additional Information for this question In the Scenario Booklet, answer the following question.

Column 1 is a list of some of the entries in the product breakdown structure. Determine whether each entry in Column 1 has been correctly shown in the product breakdown structure. Select from Column 2 the appropriate statement that correctly describes that entry. Each selection from Column 2 can be used once, more than once or not at all.

  1. See Explanation for the Answer.

Answer(s): A

Explanation:



Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)



Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).




Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Plan prerequisites section?

  1. Delete entry 2 because these are project benefits not prerequisites of the stage.
  2. Delete entry 3 because the production cost forecast is a deliverable of stage 2, not a prerequisite for stage 3.
  3. Delete entry 4 because the customer list is a deliverable of stage 2, not a prerequisite for stage 3.
  4. Add 'Engineering team must be made available for photos'.
  5. Add 'Compliance with the Data Protection Act'.

Answer(s): A,C

Explanation:

The correct answer is A and C because Plan prerequisites should only include items required to start the stage; entries about benefits or stage 2 deliverables are not prerequisites. A) Deleting entry 2 is correct since project benefits belong to the Benefits Review and not prerequisites for Stage 3. C) Deleting entry 4 is correct since the customer list is a deliverable of Stage 2, not a prerequisite for Stage 3. B) Incorrect because the production cost forecast, while used in decision-making, is still a Stage 3 prerequisite information, not a Stage 2 deliverable. D) Incorrect as it is a resourcing instruction, not a prerequisite formulation. E) Incorrect as data protection compliance is governance, not a specific prerequisite for Stage 3.



Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)



Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).



Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the External dependencies section?

  1. Delete entry 5 because the new company logo is being delivered by a separate project and will be detailed in the plans for that project.
  2. Move entry 5 to Plan prerequisites because the new company logo will influence the label designs.
  3. Move entry 5 to Plan description because the new company logo will be delivered during stage 3.
  4. Delete entry 6 because the customer details were used in stage 2 to create the customer list.
  5. Delete entry 7 because it should be shown in the Product Description for the label design.

Answer(s): D,E

Explanation:

The correct answers identify inappropriate handling of external dependencies: customer details used in stage 2 render as an external dependency no longer needed in stage 3 External dependencies, so deleting entry 7 is appropriate; similarly, since the question states none of the £500 change budget has been used and is available for the stage, deleting entry 6 is correct if it refers to budget in external context.
A) Incorrect: deletion based on separate project logo is not a valid external dependency adjustment in Stage 3.
B) Incorrect: Plan prerequisites move is not warranted; dependencies aren’t about influence on label designs.
C) Incorrect: Plan description move is not supported by stated timing of logo delivery.



Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)



Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).



Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Planning assumptions section?

  1. No change to entry 8 because this cannot be confirmed until all of the label designs entries have been received and an assessment made.
  2. Move entry 8 to External dependencies because the label designs are created outside of the scope of the project.
  3. Delete entry 9 because the photo session schedule should have been approved as part of stage 2.
  4. Move entry 9 to External dependencies because the photo session schedule is created by the professional photographer.
  5. Delete entry 10 because the inclusion of different members from the Engineering team in each photo should be shown in the Product Description for the photos.

Answer(s): A,E

Explanation:

The correct answer identifies changes to Planning assumptions that reflect re-evaluation of proof points and external dependencies.
A) No change to entry 8 because this cannot be confirmed until all of the label designs entries have been received and an assessment made. This aligns with Planning assumptions needing validation of inputs before proceeding.
E) Delete entry 10 because the inclusion of different members from the Engineering team in each photo should be described in the Product Description, not assumption entries.
B) Incorrect: External dependencies would not necessarily apply to a design entry; C) Incorrect: stage boundaries and approvals are not implied to invalidate entry 9; D) Incorrect: the photographer’s schedule as external dependency is not shown as justification for moving entry 9.



Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)



Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).



Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Monitoring and control section?

  1. Delete entry 11 because this relates to the monitoring and controlling of the Project Plan, not the Stage Plan.
  2. No change to entry 12 because this describes how the Project Board will control the stage.
  3. Move entry 12 because the Highlight Reports are deliverables of this stage and should be shown under Product descriptions.
  4. Delete entry 13 because this is part of the Controlling a Stage process.
  5. Delete entry 14 because the Product Status Account is NOT an ad-hoc report. It is produced at the end of each stage to identify any variations between planned status, reported status and actual status of the stage's products.

Answer(s): A,B

Explanation:

The correct answers identify appropriate tailoring of monitoring and control content to the Stage Plan and its products.
A) Delete entry 11 because it relates to monitoring and controlling the Project Plan, not the Stage Plan.
B) No change to entry 12 because this describes how the Project Board will control the stage.
C) Move entry 12 is wrong: Highlight Reports are not deliverables of the stage and do not belong under Product descriptions.
D) Delete entry 13 is incorrect: it is not necessarily part of Controlling a Stage.
E) Delete entry 14 is incorrect: Product Status Account is not exclusively end-of-stage; it is an ongoing control report.



Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)



Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).



Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the £500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Budgets section?

  1. Amend entry 15 because it should also include the cost of management activities.
  2. Delete entry 16 because timescales should NOT be shown under the heading of budgets.
  3. Delete entry 17 because the risk budget should be shown in the Risk Management Strategy.
  4. Add 'Change budget - £500'.
  5. Add 'Cost tolerance - +£6k 1-£6k

Answer(s): A,D

Explanation:

The correct answer: A and D
A) Amending entry 15 to include the cost of management activities is correct because Budgets must reflect all cost components, including management activities, to enable accurate forecasting and tolerance setting.
B) Deleting entry 16 is incorrect because budgets may show time-related information when it is relevant; the question concerns what belongs in Budgets, not scheduling exclusions.
C) Deleting entry 17 is incorrect because the risk budget is typically treated within the Risk Management approach, not excluded from Budgets or moved elsewhere unless the project's governance documentation specifies otherwise.
D) Adding 'Change budget - £500' is correct since a change budget exists to fund approved scope changes, and this must be recorded in Budgets.



PRINCE2 proposes 3 levels of Plan, which are they?

  1. Initiation, Project and Stage Plans
  2. Project, Stage and Exception Plans
  3. Initiation, Project and Benefit Review Plans
  4. Project, Stage and Team Plans

Answer(s): D

Explanation:

PRINCE2 defines three levels of plan: Project Plan, Stage Plan, and Team Plan, matching option D.
A) Initiation, Project and Stage Plans — incorrect because Initiation is a process activity, not a separate plan level.
B) Project, Stage and Exception Plans — incorrect; Exception Plans are contingency responses, not a formal plan level.
C) Initiation, Project and Benefit Review Plans — incorrect; Benefit Review Plans are not a plan level, and Initiation is not a plan level.
D) Project, Stage and Team Plans — correct as the three formal plan levels.