Which role is responsible for facilitating the Agilometer assessment?

  1. Project board
  2. Project manager
  3. Team manager
  4. Customer subject matter expert

Answer(s): B


Reference:

https://www.axelos.com/news/blogs/september-2019/assessing-agile-factor-prince2- agiles-agileometer



What is an epic?

  1. A detailed user story with high business value
  2. The set of products handed over to the users
  3. A high-level user story that is quite broad or vague
  4. A prioritized list of requirements to be delivered in a sprint

Answer(s): C


Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_160&showNav=true&exp andNav=true



Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

  1. To use empiricism, based on knowledge that comes from experience
  2. To build, measure, learn from your experiences
  3. To create a minimum viable product to manage uncertainty
  4. To fail fast, if you are going to fail

Answer(s): A


Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_127&showNav=true&ex pandNav=true



Which statement explains the setting of the cost tolerance for a project in an agile context?

  1. Cost tolerance is flexed
  2. Cost tolerance can be fixed or flexed
  3. Cost tolerance can be fixed and flexed
  4. Cost tolerance is fixed

Answer(s): A


Reference:

https://www.girlsguidetopm.com/inside-prince2-tolerances/#Cost_Tolerance



In Scrum, what answers the question `what can be done this sprint?'

  1. Daily scrum
  2. Sprint review
  3. Sprint planning
  4. Increment

Answer(s): A



Viewing page 7 of 20
Viewing questions 31 - 35 out of 166 questions


Post your Comments and Discuss PRINCE2 PRINCE2 Agile Foundation exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!