Which of the following products would be at the centre of any impact assessments of risks, issues and changes?

  1. Highlight Report
  2. Business Case
  3. Lessons Log
  4. Risk Management Strategy

Answer(s): B



The outputs from a PRINCE2 project are considered to be what?

  1. The business benefits
  2. Any of its tangible or intangible specialist products
  3. Its Resources
  4. The results of change

Answer(s): B



According to PRINCE2, a benefit is which of the following?

  1. An improved business operation
  2. The measurable improvement resulting from an outcome which is perceived as an advantage by one or more stakeholders
  3. The tangible or intangible product resulting from a planned activity
  4. The result of change, normally affecting real-world behaviour and/or circumstances

Answer(s): B



In PRINCE2, the information regarding the business justification for the project is normally documented in which management product?

  1. Business Case
  2. Benefits Review Plan
  3. Project Product Description
  4. Communication Management Strategy

Answer(s): A