Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

  1. Principles
  2. Themes
  3. Processes
  4. Techniques

Answer(s): A

Explanation:

The guiding obligations and good practices which determine whether a project is genuinely being managed using PRINCE2 form the 'Principles' of the method. PRINCE2 is founded on seven principles that must be present in the project management approach to consider the project being managed using PRINCE2.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is NOT one of the PRINCE2 integrated elements?

  1. Tailoring PRINCE2 to the project environment
  2. The processes
  3. The products
  4. The themes

Answer(s): C

Explanation:

In the context of PRINCE2, the integrated elements include the principles, themes, processes, and tailoring PRINCE2 to the project environment. 'The products' are not listed as one of these integrated elements. Instead, they are outputs or deliverables that result from applying the PRINCE2 methodology to project management.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

  1. Specify the desired result
  2. Provide the resources and skills to deliver the desired result
  3. Ensure the technical integrity of a project
  4. Develop a project's products

Answer(s): A

Explanation:

In the PRINCE2 customer/supplier environment, it is typically the customer's responsibility to specify the desired result of the project. This responsibility involves defining what the project should achieve in terms of outcomes and benefits, aligning with the customer's business objectives.


Reference:

PRINCE2® Foundation official study materials.



Which is a benefit of using PRINCE2?

  1. Enables the management of projects as well as of 'business as usual' activities
  2. Can be tailored by leaving out elements of the method for some projects
  3. Can be applied to any type of project
  4. Avoids the need to involve corporate or programme management

Answer(s): C

Explanation:

One of the key benefits of using PRINCE2 is its versatility and adaptability, meaning it can be applied to any type of project across various industries. This flexibility is one of the reasons PRINCE2 is widely adopted globally.


Reference:

PRINCE2® Foundation official study materials.



Which is a benefit of using PRINCE2?

  1. Is a method specifically designed for technical projects
  2. Provides for the efficient and economic use of management time
  3. Includes many of the proven planning techniques, such as critical path analysis
  4. Can be used to manage both projects and programmes

Answer(s): B

Explanation:

PRINCE2 is designed to make efficient and economic use of management time, ensuring that project management is effective without being overly bureaucratic or time-consuming. This approach helps to maximize the value received from management efforts and resources.


Reference:

PRINCE2® Foundation official study materials.



Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

  1. Specify the desired result
  2. Provide the resources and skills to deliver the desired result
  3. Pay for the project
  4. Specify the benefits of the project

Answer(s): B

Explanation:

In the PRINCE2 customer/supplier environment, the supplier's responsibility includes providing the resources and skills necessary to deliver the desired result. This involves ensuring that the necessary personnel, technology, and other resources are available to meet the project's requirements effectively.


Reference:

PRINCE2® Foundation official study materials.



Which does NOT reflect the PRINCE2 principle of continued business justification?

  1. There must be a justifiable reason for starting a project
  2. The business justification drives decision making
  3. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
  4. If a project can no longer be justified, it should be stopped

Answer(s): C

Explanation:

The principle of continued business justification in PRINCE2 means that a project must remain justified throughout its life cycle. The key factor is the project's ongoing justification, not solely its ability to deliver financial benefits. Projects may continue for reasons other than financial gain, such as strategic importance, compliance, or public safety. Therefore, stopping a project based only on financial criteria does not reflect this principle accurately.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which characteristic distinguishes a project from regular business operations?

  1. Produces benefits
  2. Introduces business change
  3. Manages stakeholders
  4. Incurs cost

Answer(s): B

Explanation:

A characteristic that distinguishes a project from regular business operations is that it introduces business change. Projects are temporary endeavors undertaken to create a unique product, service, or result, and they often drive significant changes within an organization, unlike regular operations, which are repetitive and ongoing.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Viewing page 10 of 59
Viewing questions 73 - 80 out of 463 questions