Where would the mechanism for the control of and access to a risk budget be defined?

  1. Risk Management Strategy
  2. Risk Register
  3. Risk profile
  4. Risk management procedure

Answer(s): A



Which of the following steps looks at the probability, impact and proximity of a risk?

  1. Communicate
  2. Assess (estimate)
  3. Identify (context)
  4. Plan

Answer(s): B



Which of the following steps looks at the aggregated net effect of all risks within the project?

  1. Plan
  2. Assess
  3. Implement
  4. Assess

Answer(s): D



Which of the following steps would involve the sending of information regarding project threats or opportunities to any external stakeholders?

  1. Identify
  2. Communicate
  3. Implement
  4. Plan

Answer(s): B