What is used to pass responsibility to a Team Manager for the production of one or more products?

  1. Exception Plan
  2. Work Package
  3. Product Description
  4. Checkpoint Report

Answer(s): B



Which of the following is used to inform the Project Board of a forecast deviation of stage-level tolerance?

  1. Exception Plan
  2. Exception Report
  3. Off-specification
  4. Lessons Report

Answer(s): B



To which role should a forecast breach of benefits tolerance be referred?

  1. Project Manager
  2. Executive
  3. Senior Supplier
  4. Corporate or programme management

Answer(s): D



Which is NOT an event-driven control?

  1. Highlight Report
  2. Exception Report
  3. Project Initiation Documentation
  4. End of a stage

Answer(s): A