In which product would a product's quality tolerance be defined?

  1. Project Product Description
  2. Product Description
  3. Stage Plan
  4. Quality Management Strategy

Answer(s): B



Which of the following would the Project Board only authorize one at a time?

  1. Work Packages
  2. Stages
  3. Team Plans
  4. Product Description

Answer(s): B



Which is NOT an objective of PRINCE2 stages?

  1. Provide an opportunity to assess the project viability
  2. Identify the necessary Work Packages
  3. Allow clarification of the impact of an external influence
  4. Ensure that key decisions are made prior to work needed to implement them

Answer(s): B



The Project Board needs to assess project viability at certain points as defined in the Project Plan.
How does the Progress theme assist this?

  1. Sending regular Checkpoint Reports
  2. Authorizing one stage at a time
  3. Creating Exception Reports when tolerances are threatened
  4. Reports during project closure

Answer(s): B



What is a purpose of a Daily Log?

  1. Record the products and activities planned for the stage
  2. Record actions taken to recover from issues NOT recorded in the Issue Register
  3. Record and track the status of all products produced during a stage
  4. Provide a regular update to the Project Board on the progress of the stage

Answer(s): B



The purpose of the Progress theme is to do which of the following?

  1. Identify, assess and control uncertainty
  2. To establish mechanisms to monitor and control what has happened against what is planned
  3. Facilitate communication and control by defining the means of delivering the products
  4. Define and implement the means by which the project will create and verify products which are fit for purpose

Answer(s): B



Which of the following statements are correct regarding the use of management stages?
1. Provide review and decision points
2. Enable key decisions to be made prior to the detailed work
3. Facilitate the manage by exception principle
4. Enables the project manager to have complete autonomy over the products to be produced

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): A



Which of the following are correct regarding the definition of a technical stage?
1. Technical stages never overlap
2. They are typified by the use of a particular set of specialist skills
3. Cover elements such as design, build and implementation
4. The work can be grouped by the set of techniques used

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): D